UP-RERA Property Intelligence Report

Assotech Canopy

ASSOTECHLIMITED CROSSINGS INFRASTRUCTURE PVT LTD · Ghaziabad · UP-RERA UPRERAPRJ922718

What this report covers

Filing, builder-record & plan report

This report covers:

  • the official UP-RERA filing record
  • the promoter's buyer-complaint & regulatory history
  • the builder's delivery track record
  • buyer-paperwork readiness
  • location & connectivity
  • filtered sanctioned-plan callouts

To confirm with the builder:

  • The developer did not file a dimensioned unit floor plan with UP-RERA — ask the sales team for the exact unit's plan to confirm carpet area and layout before booking.
  • 3 buyer-paperwork items still need builder/lawyer follow-up.

Report map

Declared completion
25 Jun 2026
Date in the public UP-RERA project row.
Registry completion signal
Needs OC/CC check
Verify OC/CC before treating this as ready-to-move.
Public docs
17
Plan PDFs read
4
Unit layouts
Site callouts
Buyer docs
4/7

Decision Summary

Due-diligence level
High
Regulatory & disputesLow
Completion paperworkMedium
Buyer paperworkHigh
Site-layout checkMedium

This is a verification level, not a delivery verdict. Regulatory & disputes reflects the UP-RERA buyer-complaint count and any NCLT insolvency flag. Completion paperwork asks whether the checked records show a clean OC/CC signal. Buyer paperwork summarizes document readiness. Site-layout check summarizes whether the filed plans raise tower-level follow-up questions.

Registry completion signal needs verification. The registry row shows declared completion as 2026-06-25, but the records checked for this report do not show a clean OC/CC signal. Treat this as a paperwork verification item before treating the project as ready-to-move.UP-RERA record
No usable unit layouts were readable from the filed plan set. Get the dimensioned plan for your exact unit before paying a booking amount.Filed plan
3 buyer-paperwork items need follow-up (Agreement for sale, Commencement certificate, Occupancy/completion proforma).UP-RERA record

What I'd Do As A Buyer

The shortest version of this report: specific moves for your situation, each tied to a filing or plan fact below.

If the sales team cannot give a dimensioned plan: pause until they share the filed or sanctioned plan for that exact unit.
If you need a ready-to-move home: verify completion-certificate status separately; the records checked here do not show a clean OC/CC signal.
If you are about to pay a booking amount: collect the missing or unclear buyer documents listed in the checklist and have your lawyer review them.
If the builder cannot map your flat to the sanctioned plan: do not treat facing, utility proximity, or area claims as verified.

Who This Suits & What To Verify

!Buyers comparing specific layouts should ask for a clearer unit plan before relying on area claims.
!If you need completion-certificate certainty, verify OC/possession status before treating this as ready-to-move.
Use this as a due-diligence map: it points to what to ask next, not a substitute for legal review or a site visit.

Questions To Ask The Builder

  1. Please mark my exact flat, tower, and floor on the sanctioned layout plan used for this filing.
  2. Please share the dimensioned floor plan for the exact unit being offered, not only the brochure plan.
  3. What is the current completion-certificate or occupancy-certificate status?
  4. Can you provide the missing or unclear buyer paperwork items listed in this report before booking?
  5. Which uploaded UP-RERA document should my lawyer use as the controlling version?

Official Filing Snapshot

Official fieldUP-RERA value
Project typeNew
Registration date23-09-2021
Proposed period60 months
Promoter projects on UP-RERA4
Promoter complaints on UP-RERA142 (Under Registration - 3 )
Project complaints on UP-RERA2

What the filing tells you

Synthesis from the UP-RERA record — complaint history, regulatory flags, the builder’s local delivery record, and paperwork readiness, read the way a sales team won’t volunteer.

Buyer complaints2 buyer complaint(s) are on file against this project at UP-RERA — a small count for the project itself. Separately, the promoter carries 142 complaint(s) across its UP-RERA portfolio — a heavy volume worth probing regardless of this project's own count. Complaints here usually cluster around possession delays, construction quality, or refunds; ask the builder specifically what they're about and whether any are still unresolved before you commit money.
Buyer paperworkOnly 4 of 7 key buyer/title documents are visible in the UP-RERA catalog — get the missing ones from the builder before you pay a token (see the paperwork checklist below).

Filed Plan Evidence

Development Work Plan

Development Work Plan

Filed drawing reviewed for this report

Pages: 1 · floor-plan pages found: none · site-layout pages found: none

Electricity Supply Plan

Electricity Supply Plan

Filed drawing reviewed for this report

Pages: 1 · floor-plan pages found: none · site-layout pages found: none

Water Supply Plan

Water Supply Plan

Filed drawing reviewed for this report

Pages: 1 · floor-plan pages found: none · site-layout pages found: none

Waste Disposal Plan

Waste Disposal Plan

Filed drawing reviewed for this report

Pages: 1 · floor-plan pages found: none · site-layout pages found: none

Buyer Paperwork Checklist

Buyer documentStatusUP-RERA row
Agreement for salenot listed-
Allotment letteron fileProforma of Allotment Letter
Conveyance deedon fileProforma of Conveyance Deed
Encumbrance declarationon fileDetails of Encumbrances
Form-B affidaviton fileAffidavit (Form-B)
Commencement certificatelisted, verify fileCommencement Certificate
Occupancy/completion proformalisted, verify fileProforma of Completion Certificate(Occupancy)

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Noida Expressway (Sec 125–142)6 km
Sector 62 IT hub7 km
Sector 18 commercial8 km
Connaught Place, Delhi20 km
IGI Airport, Delhi30 km
Noida Int'l Airport, Jewar54 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Document Catalog

Full uploaded-document list from the UP-RERA project page. Most rows are here for legal traceability; the earlier sections call out the buyer-relevant items.

Show full document list (17 rows)
DocumentUpload typeCategoryUse in this report
Commencement CertificateNAcomplianceListed in UP-RERA catalog
Other Plan(If Any)NAplanListed in UP-RERA catalog
Proforma of Completion Certificate(Occupancy)NAcomplianceListed in UP-RERA catalog
Other Plan(If Any)NewplanListed in UP-RERA catalog
Proforma of Allotment LetterNewcomplianceListed in UP-RERA catalog
Development Work PlanNewplanUsed in this report
ENGINEERS CERTIFICATENewcomplianceListed in UP-RERA catalog
ARCHITECT CERTIFICATENewcomplianceListed in UP-RERA catalog
CA CERTIFICATENewcomplianceListed in UP-RERA catalog
Affidavit (Form-B)NewcomplianceListed in UP-RERA catalog
Proforma of Conveyance DeedNewcomplianceListed in UP-RERA catalog
Proforma of Application FormNewcomplianceListed in UP-RERA catalog
Details of EncumbrancesNewcomplianceListed in UP-RERA catalog
Details of EncumbrancesNewcomplianceListed in UP-RERA catalog
Electricity Supply PlanNewplanUsed in this report
Water Supply PlanNewplanUsed in this report
Waste Disposal PlanNewplanUsed in this report