Project RERA record · Pune

Shree Ganesha Residency

by Tirupati Developers · MahaRERA P52100005164 · Certificate Signed · declared completion Jan 2021

No adverse MahaRERA flags

Registered with MahaRERA — no adverse flag on its public lists. Pune

Shree Ganesha Residency is registered with MahaRERA and carries no adverse flag on the regulator's public lists — no insolvency (NCLT), deregistration, suspension, completion lapse or quarterly-progress-report default. The promoter's declared completion date (Jan 2021) has passed. MahaRERA's public register does not publish occupancy/completion certificates, so it cannot confirm whether the project is delivered — this is not a delay flag (it may have completed, obtained an extension, or be running late). Confirm current possession status directly with the developer, and check the OC, sanctioned plan, title and carpet area before you commit.

Builder track record

Tirupati Developers is the promoter on 13 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Tirupati Developers

Tirupati Developers
Past its declared completion datePune

Other RERA-registered projects in Paud

Amenity Space 1 - Navyangan Phase - II
Avior Merlin Venture LLP
Anandgram Paud Phase I
Past its declared completion date Vastushodh Realty
Anandgram Paud Phase II
Past its declared completion date Vastushodh Realty
Anandgram Paud Phase III
Past its declared completion date Vastushodh Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Request the report on Shree Ganesha Residency

We analyse Shree Ganesha Residency in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Free · Risk Snapshot + alerts

The regulatory risk spine for Shree Ganesha Residency, emailed as a clean scorecard — plus an alert if the RERA status changes:

    Something went wrong — email hello@quietlist.in.

    ✓ On its way to your inbox — plus alerts if the status changes.

    Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

    Last checked against the RERA register: 11 Jul 2026