Bangalore/Project record

K-RERA · the public record

Adisesh Boulevard

· ADISESH PROJECTS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
On the registerproject recordK-RERA registration · read 16 Jul 2026

Free project details

Registration read 16 Jul 2026

Registered units and project size

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

18.1registered acres

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for Adisesh Boulevard

K-RERA · PRM/KA/RERA/1265/339/PR/210130/003806

Project facts and comparisons

On the register

Land area73,374 sq m (18.1 acres)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered land area73,374 sqmThe land area attached to this K-RERA registration.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date01-12-2018

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

17 of 30 compliance document slots are filed as Not Applicable; the remaining 13 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2023, extended (Covid Extension) to 30 Jun 2024 — both dates have passed with no OC on file.

Approval documents

Electricity (BESCOM/ESCOM)Not identified in the document list
Water & sewage (BWSSB/KWSSB)Not identified in the document list
Fire NOCNot identified in the document list
Pollution control (KSPCB)Not identified in the document list
Environmental clearanceNot identified in the document list
Airport Authority height clearanceNot identified in the document list

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Penalty orders on record:

ViolationUnder sectionPenaltyOrder date
Non Submission Of Annual Report 2021 22Section 4(2)(l)(D)₹2,570,40014/12/2023

K-RERA complaint orders (3 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Pranjal Choudhury vs Adisesh Projects & VCITI Propetech LLPRefund with interestAUTHORITY17/09/2025
Pavan Kumar Guloormutt Lokesh vs Adisesh ProjectsRequest you to take action in terms to refund my 1,20,000 INR and all the other customers in the complaint mentioned in the link aboveAUTHORITY16/06/2025
Amitraj Medhi vs ADISESH PROJECTSYes, we want RERA to intervene and take appropriate action against the construction companyAUTHORITY04/05/2026

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Builder track record

RERA filing

Adisesh Projects has 2 other K-RERA-registered projects in our records. 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: DCB Bank Jakkasandra (IFSC DCBL0000090, a/c …0578). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 13 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Whitefield IT hub13 km
Bellandur–Marathahalli belt20 km
Electronic City26 km
Outer Ring Road / Manyata29 km
MG Road / city centre29 km
Kempegowda Int'l Airport32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Adisesh Projects.
Adisesh Projects has 3 projects registered in Bangalore.
4 complaints on the K-RERA register against Adisesh Projects in Bangalore.

Other projects by this builder in Bangalore

Adisesh Green City Phase 4
No filings

Other RERA-registered projects in KASABA HOBLI

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 16 Jul 2026. Document and inventory dates are shown in their sections.