K-RERA · the public record
Adisesh Boulevard
· ADISESH PROJECTS
Project Review · example purchase
Spending a few crores on a unit? ₹4,999 to check what you’re buying.
Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.
See the report before you buy
Avoid bad decisions, only go for the best units.
Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.
Read the Project Review sample ↗From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗Free project details
Registration read 16 Jul 2026Registered units and project size
Filed categories, unchanged · K-RERA registration · read 16 Jul 2026
The whole registration
18.1registered acres
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.
RERA details for Adisesh Boulevard
K-RERA · PRM/KA/RERA/1265/339/PR/210130/003806
Project facts and comparisons
On the register
Source: K-RERA. Each comparison names the group of projects used.
Project areas, parking and inventory
Project areas and parking
RERA filing| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered land area | 73,374 sqm | The land area attached to this K-RERA registration. |
| Open-parking field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Garage field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Project start date | 01-12-2018 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingLitigation status was not supplied in the captured record. This is not confirmation that there are no cases.
17 of 30 compliance document slots are filed as Not Applicable; the remaining 13 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 31 Dec 2023, extended (Covid Extension) to 30 Jun 2024 — both dates have passed with no OC on file.
Approval documents
A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.
K-RERA enforcement record (the regulator's own defaulter list & penalty orders)
⚠ Listed on K-RERA's official DEFAULTER list.
Penalty orders on record:
| Violation | Under section | Penalty | Order date |
|---|---|---|---|
| Non Submission Of Annual Report 2021 22 | Section 4(2)(l)(D) | ₹2,570,400 | 14/12/2023 |
K-RERA complaint orders (3 complaints against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| Pranjal Choudhury vs Adisesh Projects & VCITI Propetech LLP | Refund with interest | AUTHORITY | 17/09/2025 |
| Pavan Kumar Guloormutt Lokesh vs Adisesh Projects | Request you to take action in terms to refund my 1,20,000 INR and all the other customers in the complaint mentioned in the link above | AUTHORITY | 16/06/2025 |
| Amitraj Medhi vs ADISESH PROJECTS | Yes, we want RERA to intervene and take appropriate action against the construction company | AUTHORITY | 04/05/2026 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Builder track record
RERA filingAdisesh Projects has 2 other K-RERA-registered projects in our records. 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Financials & Construction Progress
Financial disclosures
RERA filing⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.
The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.
RERA 70% project account is on file: DCB Bank Jakkasandra (IFSC DCBL0000090, a/c …0578). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Location & Connectivity
The nearest of the listed job hubs is about 13 km in a straight line from the mapped location. Road distance and travel time will differ.
| Landmark | Straight-line |
|---|---|
| Whitefield IT hub | 13 km |
| Bellandur–Marathahalli belt | 20 km |
| Electronic City | 26 km |
| Outer Ring Road / Manyata | 29 km |
| MG Road / city centre | 29 km |
| Kempegowda Int'l Airport | 32 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.