Bangalore/Project record

K-RERA · the public record

BHAVANI HESSONITE

· BHAVANI BUILDERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
16registered unitsK-RERA registration · read 16 Jul 2026

Free project details

Registration read 16 Jul 2026

Registered units and project size

3 BHK
4
1 BHK
4
2 BHK
8

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

0.2registered acres

80.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for BHAVANI HESSONITE

K-RERA · PRM/KA/RERA/1273/318/PR/110823/006161

Project facts and comparisons

On the register

Land area809 sq m (0.2 acres)
Homes registered16
Tower/wing entries1
Unit mix4 × 3 BHK, 4 × 1 BHK, 8 × 2 BHK

In context

Density80 homes per acre
Density in context47th percentile of 4913 projects in this register (median 82)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units16Total inventory registered with K-RERA.
Official carpet area1,303 sqmTotal carpet area reported for the project.
Official built-up area1,782 sqmUseful scale context when comparing density and project cost.
Registered land area809 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.54Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)15Separate filed counts; these categories may overlap and are not added together.
Covered-parking field15Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberUDP-LBPAS-17183/23-24/BPUse this to match the sanctioned drawing set shown by the builder.
Plan approval date27-06-2023
Project start date01-10-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3 BHK425%405 sqm
1 BHK425%229 sqm
2 BHK850%669 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
BHAVANI HESSONITE4161514.95 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 16 official flat/unit rows, matching the 16 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK881.2-86.0 sqm6.2-6.5 sqm8
1 BHK446.9-60.7 sqm4.1-4.9 sqm3 (1 with 0)
3 BHK4101.3 sqm7.6 sqm4

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
BHAVANI HESSONITE1646.9-101.3 sqm4.1-7.6 sqm15 (1 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1BHAVANI HESSONITE13 BHK101.3 sqm7.6 sqm1
2BHAVANI HESSONITE12 BHK86.0 sqm6.5 sqm1
3BHAVANI HESSONITE12 BHK81.2 sqm6.2 sqm1
4BHAVANI HESSONITE11 BHK46.9 sqm4.1 sqm0
101BHAVANI HESSONITE23 BHK101.3 sqm7.6 sqm1
102BHAVANI HESSONITE22 BHK86.0 sqm6.5 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

6 of 27 compliance document slots are filed as Not Applicable; the remaining 21 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Approval documents

Electricity (BESCOM/ESCOM)Document listed: ESCOM/Electricity
Water & sewage (BWSSB/KWSSB)Document listed: KWSSB/Water
Fire NOCNot identified in the document list
Pollution control (KSPCB)Not identified in the document list
Environmental clearanceNot identified in the document list
Airport Authority height clearanceNot identified in the document list

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantGANESH Y2072311998Udupi, Karnataka - 576101
EngineerM GOPAL BHATKDP-BL-10137-23-241997Udupi, Karnataka - 576101
ArchitectYOGISHCHANDRA DHARACOA/93/166791997Udupi, Karnataka - 576101
ContractorBHAVANI BUILDERS-2019Udupi, Karnataka - 576102

Builder track record

RERA filing

Bhavani Builders has 3 other K-RERA-registered projects in our records (average reported construction progress 29%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹24.1 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: STATE BANK OF INDIA UDUPI IFSC Code : SBIN0000945 Pin Code : 576101. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 309 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
MG Road / city centre309 km
Outer Ring Road / Manyata309 km
Electronic City317 km
Kempegowda Int'l Airport317 km
Bellandur–Marathahalli belt318 km
Whitefield IT hub324 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Bhavani Builders.
Bhavani Builders has 3 projects registered in Bangalore.

Other projects by this builder in Bangalore

Bhavani Emerald
Filing overdue · 58% built · 21% sold

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 16 Jul 2026. Document and inventory dates are shown in their sections.