Bangalore/Project record

K-RERA · the public record

CNM APEX CITY MADARAGALLI PH1

· Navin Kumar Gupta

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
100%construction reportedQ1 2026 filing

Free project details

Registration read 16 Jul 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q1 2026 to Q1 2026

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

RERA details for CNM APEX CITY MADARAGALLI PH1

K-RERA · PRM/KA/RERA/1268/378/PR/200626/008734

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Approved plan numberMyNaPra/NaYo/ViNa/129/2021-22Use this to match the sanctioned drawing set shown by the builder.
Plan approval date29-11-2022
Project start date29-11-2022

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

5 of 23 compliance document slots are filed as Not Applicable; the remaining 18 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

See the filed approval statuses and linked documents →

Statutory approval status

RERA filing

3 of 3 applicable approvals are marked Approved in the filing. Check the linked documents for their scope and validity.

8 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved28-12-2023KUWSSB Completion report.pdf
Engineering Department (PWD) for completion of development worksApproved09-01-2024Civil Work Completion Report.pdf
KPTCL- BESCOMApproved19-10-2023CESCOM Completion report.pdf

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantVarun Kumar Jain2515462019Mysore, Karnataka - 570007
EngineerNagaraja BMYS/BL/10783/25-262025Mysore, Karnataka - 570028

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress100% → 100% (+0 pts)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

RERA 70% project account is on file: Branch : IFSC Code : Pin Code : IFSC Code : Pin Code :. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 129 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Electronic City129 km
MG Road / city centre133 km
Bellandur–Marathahalli belt137 km
Outer Ring Road / Manyata139 km
Whitefield IT hub145 km
Kempegowda Int'l Airport158 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Navin Kumar.

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 16 Jul 2026. Document and inventory dates are shown in their sections.