Bangalore/Project record

K-RERA · the public record

Sri Ranga Enclave 7th Stage

· SRI RANGANATHA DEVELOPERS

Is this the right project?
Which unit should you choose?

Read the free RERA facts below. For help choosing a unit or comparing a price, select a report.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
On the registerproject recordK-RERA registration · read 16 Jul 2026

Free project details

Registration read 16 Jul 2026

RERA details for Sri Ranga Enclave 7th Stage

K-RERA · PRM/KA/RERA/1268/378/PR/300626/008774

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Approved plan number52:2024-25Use this to match the sanctioned drawing set shown by the builder.
Plan approval date01-03-2025
Project start date01-03-2025

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

9 of 21 compliance document slots are filed as Not Applicable; the remaining 12 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Approval documents

Electricity (BESCOM/ESCOM)Document listed: NOC from ESCOMs
Water & sewage (BWSSB/KWSSB)Not identified in the document list
Fire NOCNot identified in the document list
Pollution control (KSPCB)Not identified in the document list
Environmental clearanceNot identified in the document list
Airport Authority height clearanceNot identified in the document list

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantSurendra Hegde0296911995Mysore, Karnataka - 570002
EngineerAbishek RPE/00091/210000Mysore, Karnataka - 570017

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: KOTAK MAHINDRA BANK Siddhartha Nagar Branch IFSC Code : KKBK0008283 Pin Code : 570011. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 120 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Electronic City120 km
MG Road / city centre124 km
Bellandur–Marathahalli belt128 km
Outer Ring Road / Manyata130 km
Whitefield IT hub136 km
Kempegowda Int'l Airport148 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sri Ranganatha.
Sri Ranganatha has 2 projects registered in Bangalore.

Other projects by this builder in Bangalore

Sri Ranga Enclave 6th Stage
No filings

Other RERA-registered projects in Nagarbhavi

Construction Of 3bhk Housing Project In Sy No 103 Of Nagarbhavi Yeshwanthapura Hobli Bangalore

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 16 Jul 2026. Document and inventory dates are shown in their sections.