The Date On The Calendar

On 21 October 2026, the useful work starts for an Indirapuram buyer. UP-RERA has extended the deadline for promoters to submit the quarterly progress report for the quarter ended 30 September 2026 to that date, per Hindustan Times — Real Estate, https://www.hindustantimes.com/real-estate/up-rera-extends-quarterly-progress-report-filing-deadline-until-oct-21-101791650084202.html. UP-RERA’s own notice is dated 9 October 2026, per UP-RERA’s QPR extension notice, https://www.up-rera.in/pdf/QPR-Extension.pdf.

That date matters because Mayflower AT THE Prestige City and Mulberry AT THE Prestige City are both under construction in Indirapuram, and both carry November 2029 possession timelines in their UP-RERA project rows. The buyer action is plain: read the existing possession month now, then return after 21 October 2026 for the fresh quarterly update.

UP-RERA’s rules material says quarterly updates include booked apartments or plots and construction status with photographs, per UP-RERA’s published RERA rules PDF, https://www.up-rera.in/pdf/rera.pdf. That makes the filing more than a compliance date. It is the next public check on a live project file.

The National Pattern

Quietlist’s read of the official RERA registers shows the same buyer problem in different shapes. Maharashtra gives breadth. Bengaluru gives a dated phase-by-phase progress trail. Noida gives the immediate calendar trigger. Gurgaon gives two sector choices with QPR filings already on record.

Maharashtra is the wide scan. Sobha Inizio in Sewri is listed as under construction with possession by March 2034, per its MahaRERA project row. Bhagwati Elysia III and Bhagwati Elysia IV in Panvel are listed as under construction with possession by December 2029, per their MahaRERA project rows. Pune adds Signature Business Centre in Bhugaon, Signature Space Realty in Kirkatwadi, Prestige Business Hub in Moshi, and Prestige Platinum in Saswad, per their MahaRERA project rows.

That tells the buyer where the supply spread is. It does not by itself tell her how much progress can be compared quarter by quarter.

Bengaluru gives the cleaner progress trail in Fraser Town. Sobha Crystal Meadows Phase 2 Wing 7 And 8, Sobha Crystal Meadows Phase 3 Wing 9 To 15, Sobha Crystal Meadows Phase 4 Wing 23 To 28 and Sobha Crystal Meadows Phase 5 Wing 16 To 22 are all under construction, per their K-RERA project rows.

Their Q4 2025 QPR filings were submitted on 13 April 2026 and showed 0.0% construction progress, per each project’s Q4 2025 QPR filing with K-RERA. Phase 2 reported 59 units and 0 units sold up to registration. Phase 3 reported 59 units and 0 units sold up to registration. Phase 4 reported 42 units and 0 units sold up to registration. Phase 5 reported 93 units and 0 units sold up to registration, per their Q4 2025 QPR filings with K-RERA.

The Files With Dated Progress

Market Project Builder Locality Reg number RERA status Latest public progress filing
BengaluruSobha Crystal Meadows Phase 2 Wing 7 And 8SobhaFraser TownKA-11721Under construction; possession by June 2031Q4 2025 QPR filed 13 April 2026; construction 0.0%; 59 units; 0 units sold up to registration
BengaluruSobha Crystal Meadows Phase 3 Wing 9 To 15SobhaFraser TownKA-11745Under construction; possession by December 2032Q4 2025 QPR filed 13 April 2026; construction 0.0%; 59 units; 0 units sold up to registration
BengaluruSobha Crystal Meadows Phase 4 Wing 23 To 28SobhaFraser TownKA-11751Under construction; possession by December 2033Q4 2025 QPR filed 13 April 2026; construction 0.0%; 42 units; 0 units sold up to registration
BengaluruSobha Crystal Meadows Phase 5 Wing 16 To 22SobhaFraser TownKA-11758Under construction; possession by December 2035Q4 2025 QPR filed 13 April 2026; construction 0.0%; 93 units; 0 units sold up to registration
GurgaonSobha Aranya Phase-1SobhaSector 80RERA-GRG-1565-2024Under construction; possession by October 2030Q2 2026 QPR filed 15 July 2026
GurgaonSobha AltusSobhaSector 106RERA-GRG-1564-2024Under construction; possession by December 2031Q2 2026 QPR filed 15 July 2026

The table is the part of the shortlist where a buyer can already compare dated progress filings. Bengaluru is the clearest example because the four Fraser Town phases share the same filing date and the same reported construction percentage. That is useful. A buyer can compare the phases without guessing whether one file is much older than another.

It also says something practical about timing. A 0.0% construction figure in Q4 2025 is early-stage paper. It can suit a buyer who is comfortable waiting for a longer build-out. It is less useful for a buyer who wants to see a later progress record before booking.

Gurgaon is a different read. Sobha Aranya Phase-1 in Sector 80 shows an October 2030 possession timeline, per its Haryana RERA project row. Sobha Altus in Sector 106 shows a December 2031 possession timeline, per its Haryana RERA project row. Their Q2 2026 QPR filings were submitted on 15 July 2026, per each project’s Q2 2026 QPR filing with Haryana RERA.

Here the first question is sector and possession month. Sector 80 gives the earlier possession month in this pair. Sector 106 gives the later one. Both have dated QPR filings already visible, so the buyer is not waiting for the same 21 October trigger that matters in Noida.

Why Indirapuram Comes First

The national scan matters because it shows that the strongest buyer habit travels across markets: keep the file open after the first shortlist. But the live move is in Noida.

For the two Prestige projects in Indirapuram, the possession month is already visible in the UP-RERA rows. What changes after 21 October 2026 is the chance to put the next quarterly progress update beside that November 2029 possession timeline. That is the cleaner buyer check than comparing launch language or brochure claims.

A buyer should treat Maharashtra, Bengaluru, Noida and Gurgaon differently. In Maharashtra, start with locality and possession spread. In Bengaluru, compare the phase filings closely because the QPR data is already dated and comparable. In Gurgaon, compare sector and possession month against the filed QPR date. In Noida, come back after the UP-RERA deadline and read the new quarterly file before deciding how close the two Indirapuram options really are.

The useful shortlist is not the loudest one. It is the one where the next public document has a date. For Indirapuram, that date is 21 October 2026.