Sobha Nesara Block-3 in Kothrud carries a filed possession date of March 2027. Sobha Inizio in Sewri carries March 2034. Both name SOBHA LIMITED as promoter in their MahaRERA project records. That 7-year separation deserves more attention than a national sales headline when a household starts choosing a home: promoter preference alone cannot settle the timetable.
Outlook Money’s report on the September quarter, drawing on Anarock Research, describes rising housing sales alongside a stronger increase in launches. More developments entering the market give buyers a reason to reconsider their shortlist. The useful question is which of those choices fits the purchase they intend to make.
Quietlist’s reading of project filings across Pune, Mumbai, Indirapuram and Bengaluru shows why that question needs a project-specific answer. The Maharashtra examples have widely separated dates. The Indirapuram pair shares a completion month. Bengaluru adds a construction-reporting sequence that needs to be read in full. These differences change what a buyer should compare next.
Maharashtra’s dates have different starting points
The MahaRERA registration records place Sobha Nesara Block-3’s registration on 25 March 2019 and Sobha Inizio’s on 21 November 2025. Their registration histories therefore begin at different points, even though a buyer reviewing Kothrud and Sewri today encounters both as under-construction choices.
Registration vintage adds context to the filed timetable. It identifies when the particular development entered the register. A comparison of delivery performance would require evidence of what happened through construction and completion; the registration dates serve a different purpose here.
For a household with a preferred promoter, the immediate task is to decide which development belongs on its shortlist. A purchase intended for an approaching move and a purchase planned around a distant change in family circumstances call for different housing and payment arrangements.
Compare the registered development
The table brings together the named MahaRERA project records, the UP-RERA project summaries for Mayflower and Mulberry, and the K-RERA project record and quarterly progress filing for Crystal Meadows. Registration numbers identify the exact developments behind the comparison.
| Project and market | Filed promoter | Recorded status | Filed possession/completion date | Reported construction | Registration number |
|---|---|---|---|---|---|
| Sobha Nesara Block-3, Kothrud, Pune | SOBHA LIMITED | Under construction | 31 March 2027 | — | P52100020062 |
| Sobha Inizio, Sewri, Mumbai | SOBHA LIMITED | Under construction | 31 March 2034 | — | PR1170002501523 |
| Mayflower AT THE Prestige City, Indirapuram | PRESTIGE PROJECTS PVT. LTD. SGS CONSTRUCTION & DEVELOPERS PRIVATE LIMITED | Under construction | 13 November 2029 | — | UPRERAPRJ430385/07/2025 |
| Mulberry AT THE Prestige City, Indirapuram | PRESTIGE PROJECTS PVT. LTD. SGS CONSTRUCTION & DEVELOPERS PRIVATE LIMITED | Under construction | 27 November 2029 | — | UPRERAPRJ470993/04/2025 |
| Sobha Crystal Meadows Phase 2 Wing 7 And 8, Bengaluru | SOBHA | Under construction | 30 June 2031 | 0.0%; Q4 2025, filed 13 April 2026 | PRM/KA/RERA/1251/446/PR/280324/006734 |
These are selected project timetables, not city averages or predicted handovers; registration does not establish available homes or demand, and sales recorded up to registration do not measure quarterly sales.
Calendar months from October 2026 to selected projects’ filed dates
Calendar months
Source: Named MahaRERA, UP-RERA and K-RERA project records; one illustrative project each from Pune, Indirapuram, Bengaluru and Mumbai, selected to compare filed timetables, not city averages.
The chart makes the planning difference visible without treating an earlier date as a better home. Its usefulness depends on the household’s purpose. Someone buying for their own move should establish how the filed date fits their existing accommodation before comparing the apartment’s features.
Indirapuram narrows the date question
Mayflower AT THE Prestige City and Mulberry AT THE Prestige City lead to a different discussion. Their UP-RERA project summaries classify both as residential developments, locate them in Ghaziabad and carry the same filed promoter name shown in the table.
Mayflower’s summary records registration on 16 July 2025. Mulberry’s records 28 April 2025. Their filed completion dates nevertheless fall in November 2029, with the exact dates visible above.
Here, choosing by completion month leaves the apartment decision largely open. The productive comparison moves to carpet area, layout, orientation and the payment schedule for the particular home. Ask for those details against the exact registered development rather than treating the shared township name as a complete description of the purchase.
This is a useful contrast with Maharashtra. The Kothrud–Sewri dates help separate very different household plans. Within the Indirapuram pair, the common completion month leaves more of the choice to the home itself.
Bengaluru requires reading the sequence
For Sobha Crystal Meadows Phase 2 Wing 7 And 8, the K-RERA record carries a completion date of 30 June 2031. Its progress filings add a specific question to the purchase discussion.
The phase’s Q3 2025 QPR, filed with K-RERA on 12 January 2026, reports construction completion of 2.0%. Its Q4 2025 QPR, filed on 13 April 2026, reports 0.0%. Read these as the reported figures in those dated disclosures, without translating their difference into a claim about physical work.
The precise request to the promoter is to reconcile those disclosures: explain what each percentage covers and provide the corresponding construction certification for the same registered phase. That is more useful than asking generally whether construction is progressing. It gives the conversation a defined subject and documents against which an explanation can be checked.
What the national headline leaves to the buyer
The broader market story provides context for searching. These project records supply the questions that make the search useful. Establish the intended move, identify the registered development, then read its filed date and dated progress before assessing the apartment and payment commitments.
Choosing SOBHA LIMITED still leaves the Kothrud and Sewri dates 7 years apart. Choosing November 2029 in Indirapuram still leaves Mayflower and Mulberry to distinguish. A promoter name can narrow the search; the registered development and the particular home must finish it.