The sharp lesson from UP-RERA’s August move is not that every buyer gets a new date. It is that the official date now deserves the first read.

Hindustan Times reported that UP-RERA granted a four-month extension to eligible registered real-estate projects in Uttar Pradesh amid the West Asia crisis, subject to conditions: https://www.hindustantimes.com/real-estate/real-estate-guide/up-rera-grants-four-month-extension-to-real-estate-projects-amid-west-asia-crisis-subject-to-conditions-101787663012033.html. DD India reported that the Ministry of Housing and Urban Affairs had advised state RERA authorities to consider a four-month extension for eligible projects affected by the same disruption: https://ddindia.co.in/2026/07/govt-advises-state-reras-to-grant-4-month-extension-for-real-estate-projects-hit-by-west-asia-crisis.

For a buyer, the useful comparison is immediate. In Indirapuram, the UP-RERA Projectsummary pages for Mayflower at The Prestige City and Mulberry at The Prestige City carry November 2029 as the registered possession month. In Fraser Town, the official K-RERA rows for Sobha Crystal Meadows Phase 2 begin at June 2031 and the later phase runs to December 2035.

That is the buyer’s decision. Indirapuram is a shorter dated wait in this set. Fraser Town is a longer phased wait with richer quarterly paper. The price conversation should start only after that difference is understood.

The UP Condition Narrows The Story

Rediff, carrying the PTI report returned in the research search, stated that projects whose original, revised or previously extended completion date falls between 28 February 2026 and 31 October 2026 would be eligible for the UP-RERA extension: https://money.rediff.com/news/market/up-rera-4-month-extension-for-realty-projects-amid-crisis/53148720260825.

That window matters because the two Indirapuram examples here do not sit near it. Per Mayflower at The Prestige City’s UP-RERA Projectsummary page, the registered possession month is November 2029. Per Mulberry at The Prestige City’s UP-RERA Projectsummary page, the registered possession month is also November 2029.

Quietlist’s read of the official UP-RERA and K-RERA registers places the earliest Indirapuram date 36.4 months after the reported UP eligibility window closes. The later Indirapuram date sits 36.9 months after that same window. The earliest Fraser Town date sits 55.9 months after it.

The chart is the whole point. A state-level relief headline should not flatten the buyer’s view of time. Two projects can both be under construction, both carry known brands, and still ask for very different patience.

Indirapuram Is A Date Check, Not A Panic Check

The Indirapuram projects are simple to read. Mayflower at The Prestige City and Mulberry at The Prestige City are under construction, per their UP-RERA Projectsummary pages. Both are Prestige-branded rows in the official register. Both point to November 2029.

That gives the buyer a clean first question: is the agreement date the same as the current UP-RERA Projectsummary date? If it is, the buyer is looking at a 2029 handover story, not a near-term date caught inside the reported 2026 relief window.

This is where the UP news helps even buyers outside Uttar Pradesh. It reminds them that a registered date is not footer text. It tells them how long the purchase money may be tied to a promise before possession.

Fraser Town Is A Phased Wait With Paper

Bengaluru gives a different kind of clarity. Sobha Crystal Meadows Phase 2 Wing 7 and 8, Sobha Crystal Meadows Phase 3 Wing 9 to 15, Sobha Crystal Meadows Phase 4 Wing 23 to 28 and Sobha Crystal Meadows Phase 5 Wing 16 to 22 carry Q4 2025 QPR filings with K-RERA.

Per those Q4 2025 QPR filings with K-RERA, each of the four Fraser Town phases shows 0.0% construction progress and a filing date of 13 April 2026. Per the official K-RERA project rows, the disclosed costs are Rs 198.06 crore, Rs 177.99 crore, Rs 119.05 crore and Rs 295.46 crore. The same K-RERA rows show registered possession months from June 2031 to December 2035.

That should change how a buyer compares phases. Phase 2 is the earliest registered date in the Fraser Town set. Phase 5 is the longest wait. A buyer choosing between them is not only choosing a wing or a price point. The buyer is choosing time.

Market Project Builder Reg-number Public artifact and date Construction / status Filing units Disclosed cost
NoidaMAYFLOWER AT THE PRESTIGE CITYPRESTIGE PROJECTS PVT. LTD. SGS CONSTRUCTION & DEVELOPERS PRIVATE LIMITEDUPRERAPRJ430385/07/2025UP-RERA Projectsummary page; possession month November 2029Under constructionNot disclosed on the cited page surfaceNot disclosed on the cited page surface
NoidaMULBERRY AT THE PRESTIGE CITYPRESTIGE PROJECTS PVT. LTD. SGS CONSTRUCTION & DEVELOPERS PRIVATE LIMITEDUPRERAPRJ470993/04/2025UP-RERA Projectsummary page; possession month November 2029Under constructionNot disclosed on the cited page surfaceNot disclosed on the cited page surface
BengaluruSOBHA Crystal Meadows Phase 2 Wing 7 and 8SOBHAPRM/KA/RERA/1251/446/PR/280324/006734K-RERA Q4 2025 QPR filed 13 April 2026; registration expiry June 20310.0% construction progress59Rs 198.06 crore
BengaluruSOBHA Crystal Meadows Phase 3 Wing 9 to 15SOBHAPRM/KA/RERA/1251/446/PR/280324/006735K-RERA Q4 2025 QPR filed 13 April 2026; registration expiry December 20320.0% construction progress59Rs 177.99 crore
BengaluruSOBHA Crystal Meadows Phase 4 Wing 23 to 28SOBHAPRM/KA/RERA/1251/446/PR/280324/006736K-RERA Q4 2025 QPR filed 13 April 2026; registration expiry December 20330.0% construction progress42Rs 119.05 crore
BengaluruSOBHA Crystal Meadows Phase 5 Wing 16 to 22SOBHAPRM/KA/RERA/1251/446/PR/280324/006737K-RERA Q4 2025 QPR filed 13 April 2026; registration expiry December 20350.0% construction progress93Rs 295.46 crore

The National Read Is Selective, Not Flat

The wider official register set spans Maharashtra, Bengaluru, Noida and Gurugram. That breadth is useful, but it should not distract from the sharper choice.

Gurugram’s Sobha examples show why the same calendar method travels. Per the H-RERA row, Sobha Altus in Sector 106 is under construction with registration expiry in December 2031. Its Q2 2026 filing is dated 15 July 2026 and carries 296 filing units. Per the H-RERA row, Sobha Crescent Phase - 1 in Sector 71 carries March 2033 as the registered end month.

Maharashtra adds place spread. Per the MahaRERA rows, Sobha Inizio in Sewri is under construction with possession by March 2034, while Bhagwati Elysia III and Bhagwati Elysia IV in Panvel carry December 2029. The Pune rows include Bhugaon, Moshi and Saswad, with stated possession months from December 2027 to January 2030.

Those markets confirm the method. They do not replace the main conclusion.

The Buyer Judgement

The Indirapuram buyer should treat November 2029 as the starting fact and ask whether the current UP-RERA Projectsummary page matches the builder’s paperwork. The Fraser Town buyer should go further: compare the phase date and the latest K-RERA QPR before comparing the payment plan.

That is the reported conclusion from this set. Noida’s Prestige City examples are closer dated and less granular on the cited public surface. Bengaluru’s Sobha Crystal Meadows phases are later dated and more granular in quarterly filings. One asks the buyer to verify the current official date. The other asks the buyer to choose the right phase of a long programme.

UP-RERA’s four-month relief has made the date visible. The buyer’s job is to keep it visible after the headline fades.