Mumbai/Project record

MahaRERA · the public record

Avhni

Dronagiri · Aaum Constructions

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Sep 2021declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Avhni

MahaRERA · P52000016672

Delivery and registration

When is the project declared for completion?

Avhni is registered with MahaRERA as P52000016672 and the promoter has declared completion for 30 Sep 2021.

30 Sep 2021

declared completion

61months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52000016672
Registered on05 Jun 2018
Promoter-declared completion30 Sep 2021
Current statusCertificate Signed
Against todayabout 61 months past the declared date

Promoter record

What else is this promoter on record for?

Aaum Constructions is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Avhni in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Avhni1G+531 Mar 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2021he Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprece

Location, Land & Connectivity

Located at Dronagiri, Plot No 148, Sector 51, Thane, Thane, 400702. Per the filed land record, the plot is bounded to the north by 11 Mts Wide Road, to the south by Plot No 137, to the east by Plot No 147 and to the west by Plot No 149. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dronagiri

Siddhivinayak Apartments
declared completion Nov 2026 · Baldev Diwan Singh
Phoenix
declared completion Dec 2026 · Adarsh Enterprises
Aaradhy Heights
declared completion Dec 2026 · Lambodar Infra
Avantika Aura
declared completion Dec 2026 · Riddhi Developer
Bombay Chalet
declared completion Dec 2026 · Bombay Shiva Plus LLP
Dream Plaza
declared completion Dec 2026 · Imran Subhan Ahmed
More projects in Raigarh

Other RERA-registered projects in Raigarh

Avighna
declared completion Mar 2023 · Rati Developers
Avighna
declared completion Dec 2026 · Shinde And Vichare Ventures
Avion
declared completion Dec 2029 · Surana Commercials Private Limited
Avnit Plaza
declared completion Oct 2025 · Avnit Enterprise
Ayaana
declared completion Dec 2030 · Shree Sai Developers
Ayan Skyway
declared completion Sep 2026 · Ibrahim Nazirsha Mukadam

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 11 Sep 2026. Document and inventory dates are shown in their sections.