Mumbai/Project record

MahaRERA · the public record

CLAN CITY-AQUA MARINE

TALOJA · Supreme Construction and Developers Private Limited

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
29 Mar 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for CLAN CITY-AQUA MARINE

MahaRERA · P52000002531

Delivery and registration

When is the project declared for completion?

CLAN CITY-AQUA MARINE is registered with MahaRERA as P52000002531 and the promoter has declared completion for 29 Mar 2024.

29 Mar 2024

declared completion

31months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52000002531
Registered on01 Aug 2017
Promoter-declared completion29 Mar 2024
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CLAN CITY-AQUA MARINE record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

Supreme Construction and Developers Private Limited is the promoter of record on 9 projects registered with MahaRERA.

9projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CLAN CITY-AQUA MARINE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+38.

BuildingWingsFloorsDeclared completion
AQUA MARINE1G+3831 Mar 2022

Legal and disputes

What disputes are disclosed?

34 complaints are on the MahaRERA record for CLAN CITY-AQUA MARINE, with orders passed in 32 of them.

34complaints

32with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019769122/07/2021Mr. Vijay Mishrani vs Supreme Construction & Developers Pvt. Ltd.order passed
CC00600000016129818/10/2019RAMESH JOSHI vs SUPREME CONSTRUCTION AND DEVELOPERS PVT LTDorder passed
CC00600000019697717/05/2021Rajshekhar Swami vs Supreme Construction and Developers Private Limitedorder passed
CC00600000019850829/09/2021URMILA THAKUR vs MANULLA MEHBULLAH KANCHWALAorder passed
CC00600000022092401/05/2022URMILA THAKUR vs MANULLA MEHBULLAH KANCHWALAorder passed
CC00600000019923001/12/2021Subhash Chandra Agarwal vs Supreme Construction & Developers Pvt. Ltd.order passed
CC00600000022093322/04/2022Gurcharan Singh Talwar vs Supreme Construction and Developer Pvt Ltdorder passed
CC00600000025177407/07/2022Nanda Maheswari vs M/s. Supreme Construction and Developers Pvt. Ltd.order passed
CC00600000026194218/07/2022Mr. Bhupesh Singh and Mrs. Alka Bhupesh Singh vs M/s. Supreme Constructions and Developersorder passed
CC00600000026194318/07/2022Mrs. Alka Bhupesh Singh and Mr. Bhupesh Singh vs M/s. Supreme Constructions and Developersorder passed
CC00600000033396315/01/2023Chander Parkash vs Supreme construction and developers pvt ltdorder passed
CC00600000033406331/01/2023Nilkanth Arjun Masane vs Supreme Construction and Developers Pvt. Ltd.order passed
CC00600000033414430/01/2023Mrs Shubhada Satish Nene vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000034418401/02/2023Mr Rajaram Bajirao Bhosale vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000034426809/02/2023Mrs Smeeta S Lad Mr Amit S Lad Mrs Payal A Lad vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000035434815/02/2023Jitesh Kumar Chouhan vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000035434915/02/2023Mrs Seemakurthi Bramara Prasad and Mr Seemakurthi Nagaprasad vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000035435015/02/2023Shailendra Kumar Mittal and Asha S Mittal vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000037499528/03/2023Mrs Olive Peter Fernandes and Mr Peter Fernandes vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039602001/06/2023Mr Irfan Muniruddin Shaikh vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039637021/06/2023Mr Mohammad Abbas Nathani and Mrs Ehnaz M Nathani vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039681324/07/2023Shivshankar Ramkedar Dubey vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000039690101/08/2023Sanjay Mithailal Dubey vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000047978526/03/2024Dayanand Shantaram Lad vs Supreme Construction and Developers Pvt Ltdorder passed
CC00600000058084609/07/2024Kanchan Sharma vs Supreme Developers & Construction Pvt Ltdorder passed
CC00600000058095027/06/2024Hilary Stevan Rego vs Supreme Construction and Developers Pvt Ltdorder passed
CC1250064724/02/2025ClanCity Welfare association vs Supreme Construction and Developers Private Limitedorder passed
CC1260013909/01/2026Sanket Omprakash Jhaver vs Supreme Construction and Developers Private Limitedorder passed
CC1250160515/05/2025Mohd Ayub Mohd Hanif Qureshi vs Supreme Construction and Developers Private Limitedorder passed
CC1250346028/09/2025Manju Ashok Kharwad vs Supreme Construction and Developers Private Limitedorder passed
CC1250391007/11/2025Deepak Nambiar vs Supreme Construction and Developers Private Limitedorder passed
CC1250423029/11/2025Rajiv Mendiratta vs Supreme Construction and Developers Private Limitedorder passed
CC1260038020/01/2026Dilip Agrawal vs Supreme Construction and Developers Private Limitedpending / no order on file
CC1260052730/01/2026Shrikant Mane vs Supreme Construction and Developers Private Limitedpending / no order on file

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. Filed descriptions (status fields empty): 3 “FINAL ORDER PASSED MATTER DISPOSED”; 1 “Pending”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court340,348,342,343,351,344,3492017Status not supplied
Filed description: FINAL ORDER PASSED MATTER DISPOSED
Bombay High Court77,79,84,80,75,74,762017Status not supplied
Filed description: FINAL ORDER PASSED MATTER DISPOSED
Bombay High Court191,192,193,194,195,310,3112017Status not supplied
Filed description: FINAL ORDER PASSED MATTER DISPOSED
Bombay High Court202742017Status not supplied
Filed description: Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Mar 2024This project has a special status as it is in collaboration with regional planning authority, MMRDA, constituted by the state Government. As per the role defined in the scheme, the

Location, Land & Connectivity

Located at TALOJA, NH4, Mumbai City, Mumbai City, 410208. Per the filed land record, the plot is bounded to the north by Survey No 58, to the south by Tower No 8 Emerald, to the east by Open Sapce and to the west by Open Space. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 19 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park19 km
Bandra Kurla Complex (BKC)22 km
Chhatrapati Shivaji Int'l Airport22 km
Andheri MIDC / SEEPZ22 km
Lower Parel / Worli business district28 km
Nariman Point / Fort32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Supreme Construction And Developers Private L project & its RERA track record →

Other RERA-registered projects in Taloja

Om Unnati
declared completion Nov 2026 · Om Group
Arihant Amisha Phase II
declared completion Dec 2026 · Arihant Aashiyana Private Limited
Arihant Anant
declared completion Dec 2026 · Mahalaxmi Cotton Mills
Orchid Enclave
declared completion Dec 2026 · Siddhivinayak Associates
SAI Suncity Commercial
declared completion Dec 2026 · Chariot Properties LLP
Sarvam
declared completion Dec 2026 · Ashtvinayak Homes
More projects in Raigarh

Other RERA-registered projects in Raigarh

Clan City-Diamond
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City-Emerald
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City-Garnet
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City-Pearl
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City-Ruby
declared completion Mar 2024 · Supreme Construction And Developers Priv
Clan City - Sapphire
declared completion Mar 2024 · Supreme Construction And Developers Priv

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.