Happy Homes

Khalapur · Harjinder Kaur Charandeep Singh

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

11units filed as unsoldInventory · 24 October 2026
30 Mar 2026declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 19 Jul 2026

RERA details for Happy Homes

MahaRERA · P52000029102

Delivery and registration

When is the project declared for completion?

Happy Homes is registered with MahaRERA as P52000029102 and the promoter has declared completion for 30 Mar 2026.

30 Mar 2026

declared completion

7months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP52000029102
Registered on26 Apr 2021
Promoter-declared completion30 Mar 2026
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Happy Homes record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 19 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-09-30).

What the filings record, unit by unit

Read from MahaRERA on 24 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 14 units carry one, and 11 of the 25 are recorded unsold.

Here is one unit filed as unsold, beside the amounts filed for comparable units:

UnitCarpetFiled comparisonBased on
204280 sqftRs 20.50 lakh typical, over Rs 19.00 lakh to Rs 20.50 lakh6 filed · similar area (within 2%), elsewhere in project

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today.

In Happy Homes, every one of the 11 unsold units has filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See the other 10 units — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Happy Homes1G+631 Mar 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2024In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reas
30 Mar 202430 Mar 2026In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r

Location, Land & Connectivity

Located at Khalapur, Plot No -126/5, Panvel, Raigarh, 410222. Per the filed land record, the plot is bounded to the north by Survey No - 125 Part, to the south by Survey No - 125, to the east by Survey No -127 and to the west by 7 point 50 Mtr wide road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 40 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park40 km
Bandra Kurla Complex (BKC)40 km
Nariman Point / Fort40 km
Lower Parel / Worli business district41 km
Chhatrapati Shivaji Int'l Airport42 km
Andheri MIDC / SEEPZ44 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Rees

Balaji Tulips
declared completion Nov 2026 · Balaji Homes
Latitude-Status Redefined
declared completion Dec 2026 · Flexton Lifespaces Private Limited
Jyoti Residency
declared completion Mar 2027 · Janvi Enterprises
Shree Aangan - A Wing
declared completion Dec 2027 · Shiv Creators LLP
Triratna Complex
declared completion Dec 2027 · Empire Builders AND Developers
Aashray Nisarg
declared completion Jun 2028 · Aashray Homes
More projects in Raigarh

Other RERA-registered projects in Raigarh

Harbour City Sector-I
declared completion Mar 2018 · Garva Land Deal Private Limited
Harbour City Sector-III
declared completion Mar 2019 · Garva Land Deal Private Limited
Harbour City Sector-IV
declared completion Sep 2020 · Garva Land Deal Private Limited
Hari Niwas
declared completion Sep 2020 · Hari Krishna Buildcon
Hari Niwas
declared completion Dec 2030 · Globe Infra Developers 1
Hari Om
declared completion Dec 2025 · Hezal Infrastructure

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.