Mumbai/Project record

MahaRERA · the public record

KELVE PARADISE A WING

S S PARK KELVE ROAD · SHEETALREALITY

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for KELVE PARADISE A WING

MahaRERA · P99000021539

Delivery and registration

When is the project declared for completion?

KELVE PARADISE A WING is registered with MahaRERA as P99000021539 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

10months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000021539
Registered on08 Jul 2019
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KELVE PARADISE A WING record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KELVE PARADISE A WING in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
KELVE PARADISE1G+431 May 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2025Due to delay in grant of CC and Labour & material supply

Location, Land & Connectivity

Located at S S PARK KELVE ROAD, KELVE ROAD, Palghar, Palghar, 401401. Per the filed land record, the plot is bounded to the north by GUT NO 193 GOANTHAN, to the south by GUT NO 43 AND 142, to the east by GUT NO 1 AND 41 and to the west by GUT NO 44. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kelve Road

Karrm Brahmaand Affordable Homes PVT LTD
Not filing quarterly progress reports · declared completion Dec 2026 · Karrm Brahmaand Affordable Homes Private
Bhaskar Save Nagar
declared completion Dec 2026 · Sai Builders And Developers
Rose Heights
declared completion Dec 2026 · Mehandi Hasan Sarif Shalmani
Savera Complex
Not filing quarterly progress reports · declared completion Dec 2026 · Savera Builders & Developers
THE Hill Touch
declared completion Dec 2026 · Aristone Infra
SK Swarnik Homes
declared completion Feb 2027 · SK Swarnik Homes
More projects in Palghar

Other RERA-registered projects in Palghar

Keshav-2
declared completion Dec 2028 · Atul Rajnikant Desai & Others
Keshav 3
declared completion Dec 2029 · Aditya Naresh Patil
Keshav ONE
declared completion Sep 2023 · Keshav Enterprises
Keshav Srushti
declared completion Dec 2025 · Srushti Realtors
Keziah Enclave
declared completion Dec 2024 · Keziah Construction
KGN Complex
declared completion Sep 2026 · KGN Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 11 Sep 2026. Document and inventory dates are shown in their sections.