KOEYNA EMPIRE

PALGHAR · A V GROUP

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Mar 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for KOEYNA EMPIRE

MahaRERA · P99000019403

Delivery and registration

When is the project declared for completion?

KOEYNA EMPIRE is registered with MahaRERA as P99000019403 and the promoter has declared completion for 31 Mar 2025.

31 Mar 2025

declared completion

19months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000019403
Registered on29 Jan 2019
Promoter-declared completion31 Mar 2025
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KOEYNA EMPIRE record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KOEYNA EMPIRE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BUILDING NO 5, WING A1G+429 Sep 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered28 Mar 2022DUE TO SOME UNAVOIDABLE REASONS THE PROJECT COULD NOT BE COMPLETED ON OR BEFORE THE DUE DATE
28 Mar 202231 Mar 2025DUE TO SOME UNAVOIDABLE REASONS THE PROJECT COULD NOT BE COMPLETED ON OR BEFORE THE DUE DATE

Location, Land & Connectivity

Located at PALGHAR, BUILDING NO 5, WING A GUT NO 140,156 DISTRICT PALGHAR 401501, Palghar, Palghar, 401501. Per the filed land record, the plot is bounded to the north by GUT NO 153 AND 157, to the south by GUT NO 135, to the east by GUT NO 142 AND 155 and to the west by GUT NO 136 AND 139. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Boisar

Marathe Complex
declared completion Dec 2026 · Gprs Realty
Rajhans United Regency III
declared completion Dec 2026 · Rajhans Homes
Yash Padma
declared completion Dec 2026 · SAI Shraddha Enterprises
Avani Residency
declared completion Dec 2026 · Avani Residency
Avasar Residency
declared completion Dec 2026 · Amico Builder
Bhakti Apartment Phase II
declared completion Dec 2026 · Saryu Builders & Developers
More projects in Palghar

Other RERA-registered projects in Palghar

Kotak Kunj
declared completion Apr 2019 · Pradeep Kisandas Kotak
Kotak Royale
declared completion Jun 2026 · Level Up Realtors
Krisha Apartment
declared completion Dec 2027 · Krisha Builders
Krisha Arcade
declared completion Dec 2027 · Nine Builders & Developers
Krisha Heights
declared completion Mar 2028 · The Empire Infra
Krishna Apartment
declared completion Dec 2022 · Ashok Thakorbhai Patel

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.