MAHALAXMI RESIDENCY

NEAR NUTAN HIGH SCHOOL · ARPITA REALTORS AND INFRA PRIVATE LIMITED

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for MAHALAXMI RESIDENCY

MahaRERA · P99000014281

Delivery and registration

When is the project declared for completion?

MAHALAXMI RESIDENCY is registered with MahaRERA as P99000014281 and the promoter has declared completion for 31 Dec 2022.

31 Dec 2022

declared completion

46months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000014281
Registered on20 Nov 2017
Promoter-declared completion31 Dec 2022
Current statusCertificate Signed
Against todayabout 46 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MAHALAXMI RESIDENCY record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MAHALAXMI RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
MAHALAXMI RESIDENCY1G+710 Dec 2018

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for MAHALAXMI RESIDENCY, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000010034931/07/2019AMIT VISHWANATH SAWANT vs ARPITA REALTORS AND INFRA PVT LTDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered10 Dec 2020DUE TO LABOUR SHORTAGE, CHANGE IN SUB CONTRACTOR DUE TO SUB STANDARD IN CONSTRUCTION AND INCLEMENT WEATHER
10 Dec 202031 Dec 2022DUE TO LABOUR SHORTAGE AND TURNOVER OF LABOUR AT CONSTRUCTION SITE WAS VERY MUCH HIGH AND DUE TO COVID-19 PANDEMIC AS CONSTRUTION WAS NOT AN ESSENTIAL SO, OUR WORK WAS CLOSED

Location, Land & Connectivity

Located at NEAR NUTAN HIGH SCHOOL, VIRAR ROAD, Vasai, Palghar, 401209. Per the filed land record, the plot is bounded to the north by NUTAN HIGH SCHOOL GATE, to the south by ST ANTHONY HIGH SCHOOL, to the east by VIRAR ROAD and to the west by NUTAN HIGH SCHOOL. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 34 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ34 km
Powai / Hiranandani business park36 km
Chhatrapati Shivaji Int'l Airport38 km
Bandra Kurla Complex (BKC)41 km
Lower Parel / Worli business district48 km
Nariman Point / Fort56 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara East

N G Platinum City
declared completion Dec 2026 · J M G Realtors PVT LTD
Rudra Heights Bldg NO 1 Wing -G
declared completion Dec 2026 · Aura Navkar Developers
Ajay CO-Operative Housing Society LTD
declared completion Dec 2026 · MAA Guru Construction
Imperialparamount
declared completion Dec 2026 · Shivganga Construction & Redeveloper
Precilla CHS LTD
declared completion Dec 2026 · Blue OAK Infrastructure
Samaira Residency
declared completion Dec 2026 · AV Crystal Space
More projects in Palghar

Other RERA-registered projects in Palghar

Maharudra Residency
declared completion Dec 2026 · SAI Shraddha Enterprises
Mahavir Arcade
declared completion Dec 2028 · Mahavir Developers AND Realtors
Mahavir Ashish CO-Operative Housing Society LTD
declared completion Dec 2026 · Yashraj Developers
Mahavir Business Centre
declared completion Dec 2026 · Rajesh Developers
Mahavir Complex
declared completion Dec 2024 · Vinayak Builders
Mahavir Darshan
declared completion Dec 2025 · Mahavir Realtors

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.