NARMADA VIHAR

Thane · K.M.DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for NARMADA VIHAR

MahaRERA · P99000006696

Delivery and registration

When is the project declared for completion?

NARMADA VIHAR is registered with MahaRERA as P99000006696 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000006696
Registered on16 Aug 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NARMADA VIHAR record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

K.M.DEVELOPERS is the promoter of record on 3 projects registered with MahaRERA.

3projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NARMADA VIHAR in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BUILDING NO 11G+431 Aug 2019
BUILDING NO 21G+431 Jul 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Aug 2020WE NEED TO MODIFY OUR PROJECT DETAILS AS WE HAD MENTIONED 2 BLDG IN A SINGLE PROJECT WE NEED TO CHANGE BOTH THE BUILDINGS AS SEPARATE PROJECT AND SEPARATE DATE OF COMPLETION. AT PR
30 Aug 202031 Dec 2023We had started project and done the plinth work till date, but due to no sale of flats and shops we are slowly doing construction work, so there is delay in construction. Also as t

Location, Land & Connectivity

Located at Thane, Thane, 401504. Per the filed land record, the plot is bounded to the north by BUILDING NO 3, to the south by BOISAR KURGAON ROAD, to the east by BOUNDARY WALL and to the west by INTERNAL LAYOUT ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 80 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ80 km
Powai / Hiranandani business park82 km
Chhatrapati Shivaji Int'l Airport84 km
Bandra Kurla Complex (BKC)87 km
Lower Parel / Worli business district93 km
Nariman Point / Fort101 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pasthal

Mahavir Business Centre
declared completion Dec 2026 · Rajesh Developers
Balaji Complex Phase-2
declared completion Dec 2027 · B R Housing
Mahavir Neytra
declared completion Dec 2027 · Rajesh Construction
Mahavir Vihar Building NO 4 Type E
declared completion Dec 2027 · Rajesh Construction
Shree Samarth Apartment
Not filing quarterly progress reports · declared completion Dec 2027 · Aakash Keshmani Singh
Ramsetu
declared completion Aug 2029 · Satvik Builders & Developers
More projects in Palghar

Other RERA-registered projects in Palghar

Natraj
declared completion Dec 2028 · Canopy Infra
Naval Baug Building No 1 And 2B
declared completion Mar 2022 · Ahura Mazda Developers
Navkar City
declared completion Dec 2021 · Navkar Developers
Navkar City Phase I Part 14
declared completion Dec 2028 · Navkar Developers
Navkar City Phase I Part 2
declared completion Dec 2026 · Navkar Estate And Homes Pvt Ltd
Navkar City Phase-I-Part-4
declared completion Dec 2026 · Navkar Estate & Home Pvt Lts

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.