Neumec Niwara

P51800003319 · Vile Parle East · promoter Neumec Venture

The Drawings Report · ₹4,999

Which home should you ask for in Neumec Niwara?

We read all 4 approved drawings and 27 filed papers on this project’s RERA file — the sheets the builder filed to get it approved.

All 16 homes sold in the latest filing · 8 in 10 of the 16 registered agreements between ₹10,073 and ₹47,878 per sq ft of carpet · 51.4% of the project cost incurred · completion date revised 5 times.

  • Which home to ask for — and which to say no to
  • What the drawings put around it
  • What to get in writing before you pay a booking amount

One real find, from a Gurugram colony’s approved papers: 392.997 sq m already used of the 396 allowed — the promised extra room can never be built.

Get it for this project →

Not useful to your decision? Full refund — no questions asked. Sent as a PDF in one working day.

Free before you decide: the 14 things to get in writing before you book

Every item comes from a real RERA filing. Send it to the family group before anyone pays a token.

Read it here →

Delivery and registration

When is the project declared for completion?

Neumec Niwara is registered with MahaRERA as P51800003319 and the promoter has declared completion for 30 Sep 2027.

30 Sep 2027

declared completion

12months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800003319
Registered on05 Aug 2017
Promoter-declared completion30 Sep 2027
Current statusCertificate Signed
Against today12 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Neumec Niwara record 33 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

Promoter record

What else is this promoter on record for?

Neumec Venture is the promoter of record on 10 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Neumec Niwara, ₹6.00 Cr of a declared ₹11.68 Cr estimated project cost is reported as incurred, about 51.4%, as at the last certified filing with MahaRERA.

51.4%

₹6.00 Cr

of ₹11.68 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Neumec Niwara, 16 of 16 homes filed with MahaRERA are recorded as sold or booked, about 100%, and 0 remain available.

100%sold

16 of 16 homes

₹19.34 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹13.43 Cr (about 69%) is recorded as collected and ₹5.91 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 16 registered agreements, the effective carpet rate is ₹23,695/sqft, with eight in ten falling between ₹10,073 and ₹47,878 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 04 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 16 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is what was registered for one {unit}. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the {unit} is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

Every home in Neumec Niwara is filed sold or booked, so there is no asking price left to test — but the record of what this project sold for is complete. The Sales Report lists all 16 registered agreements: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 16 registered agreements — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10 and 16 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
NEUMEC NIWARA1G+1016-

Unit mix on the filing: 14 residential and 2 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Neumec Niwara, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000167002/11/2017Parshuram Mahadev Shirsat vs Mr. Nilesh H. Gunjal,Mr. Ghevarchand Jain,Mr. Rajesh Jainorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 5 times, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2020REASON EXPLAINED IN ATTACHMENT
30 Mar 202030 Jun 2022The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprec
30 Jun 202231 Mar 2025In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r
31 Mar 202530 Sep 2026The delay was mainly occurred due to realignment of PG reservation on the Project land and obtaining various sanctions approvals etc. from the competent authority in that behalf in
30 Sep 202630 Sep 2027The project completion has been delayed due to pending finishing and development work, along with delays in obtaining necessary approvals from concerned authorities. The remaining

Location, Land & Connectivity

Located at Vile Parle East, Mumbai Suburban, Ward ABCD, Mumbai City, 400057. Per the filed land record, the plot is bounded to the north by 420, to the south by 418B, to the east by 418 C1 and to the west by 418B. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport2 km
Andheri MIDC / SEEPZ4 km
Bandra Kurla Complex (BKC)4 km
Powai / Hiranandani business park6 km
Lower Parel / Worli business district12 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 What I’d do as a buyer here · Drawings Report

The report opens with what this project really is — read from its approved drawings — then the specific calls: the cheapest good way to buy here, the home to say no to, what you can stop worrying about, and what to get in writing before you sign anything.

Unlock in the ₹4,999 report →

Site & infrastructure

What this project's sanctioned plan shows — read for you
Where the plan is legible, the full report reads this project's layout plan filed with MahaRERA and lays out what's on it: where the utilities and open space sit, how the site is laid out around them, and which way it faces. When a plan can't be read clearly, we tell you plainly rather than guess.
In the full report:Open space · Utilities · Orientation · Layout
See what the full read covers ↓or read a sample report first →

🔒 Which home to ask for · Drawings Report

The home-level read: which ones to prefer and which to avoid, what the drawings put around each, and the things on this site nobody at the sales desk will tell you about.

Unlock in the ₹4,999 report →

The approved drawings

4approved drawings on file
27other papers filed

Everything above is on this page already, free, from the government record. The drawings are different: the 4 approved sheets are the same drawings the builder filed to get Neumec Niwara approved — what sits under each tower, which floor holds machines, what the sales sheet leaves out. Nobody reads them for you. We do.

What that turns up — from other projects’ filings:

ATS Knightsbridge · Sector 124, Noida

You pay for 10,000 sq ft. The floor inside your home is 6,982 sq ft. The rest is walls, shared circulation and services. Get both numbers written into your agreement before you pay any booking amount.

Oberoi Elysian · Goregaon East, Mumbai

“The building is complete.” The tower has reached full height — true. The same filed certificate, same page: sanitary fittings 6% done. Ask for a possession date in writing.

Godrej Aristocrat · Sector 49, Gurugram

Paying extra for the top floor? The terrace drawing shows what sits on the slab above those flats: the overhead water tanks, the lift machine rooms and the roof machinery. Ask which flat sits under which.

Prestige Camden Gardens · Thanisandra, Bengaluru

The approved parking table asks for 12 visitor spaces. It shows 0. Two-wheeler spaces: also 0. Ask in writing where visitors will park.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Neumec Venture is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Neumec Venture

Neumec Venture
FlaggedMumbai Suburban

Other RERA-registered projects in Vile Parle East

Moti Madhav
possession by Sep 2026 · Aadhya Skyvista
Yeshwant Sadan
possession by Sep 2026 · ARG Life Spaces LLP
Vile Parle Mamata Chsl
possession by Oct 2026 · Dhruv Infrastructure
Vanmala Nivas CHS LTD
possession by Nov 2026 · AMI Infra Realtors
ZEE Nayak
possession by Dec 2026 · Pragatee ZEE
ZEE Shaan
possession by Dec 2026 · Trisul Developers

Other RERA-registered projects in Mumbai Suburban

Neumec Srushti
possession by Dec 2027 · Neumec Estate Developer LLP
Neumec Vinayak
declared completion Sep 2020 · Neumec Venture
NEW Aakanksha Chsl
possession by Feb 2028 · Hirani Realty
New Abhiram CHS LTD
declared completion Sep 2025 · Peerless Constructions Pvt. Ltd.
New Aishwarya
declared completion Jan 2020 · Prabhakar Shetty
NEW Anamika Triveni Fortune
declared completion Dec 2017 · Triveni Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 10 Sep 2026