Mumbai/Project record

MahaRERA · the public record

PADMAVATI COMPLEX

BOISAR · DIVYA JYOTI ENTERPRISES

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
15 Dec 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for PADMAVATI COMPLEX

MahaRERA · P99000005325

Delivery and registration

When is the project declared for completion?

PADMAVATI COMPLEX is registered with MahaRERA as P99000005325 and the promoter has declared completion for 15 Dec 2022.

15 Dec 2022

declared completion

46months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000005325
Registered on11 Aug 2017
Promoter-declared completion15 Dec 2022
Current statusCertificate Signed
Against todayabout 46 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PADMAVATI COMPLEX record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

DIVYA JYOTI ENTERPRISES is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PADMAVATI COMPLEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
PADMAVATI COMPLEX BLDG NO 21G+531 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered15 Jun 2022WORK IS COMPLETED FULLY. PROCESS FOR OC IS GOING ON

Location, Land & Connectivity

Located at BOISAR, BOISAR, Thane, Thane, 401501. Per the filed land record, the plot is bounded to the north by 19495787N72432083E, to the south by 19495686N72432200E, to the east by 19495758N72432159E and to the west by 19495715N72432118E. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 80 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ80 km
Powai / Hiranandani business park82 km
Chhatrapati Shivaji Int'l Airport84 km
Bandra Kurla Complex (BKC)87 km
Lower Parel / Worli business district94 km
Nariman Point / Fort101 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Boisar

Marathe Complex
declared completion Dec 2026 · Gprs Realty
Rajhans United Regency III
declared completion Dec 2026 · Rajhans Homes
Yash Padma
declared completion Dec 2026 · SAI Shraddha Enterprises
Avani Residency
declared completion Dec 2026 · Avani Residency
Avasar Residency
declared completion Dec 2026 · Amico Builder
Bhakti Apartment Phase II
declared completion Dec 2026 · Saryu Builders & Developers
More projects in Palghar

Other RERA-registered projects in Palghar

Padmavati Complex
declared completion Dec 2025 · Divya Jyoti Enterprises
Padmavati Residency-I
declared completion Sep 2020 · Siddhidata Developers
Padmi Hari Complex
declared completion Dec 2025 · Aashirwad Developers
Palacia
declared completion Aug 2027 · M/s. Sagar Developers
Palash Apartment
declared completion Mar 2027 · Palash Buildcon
Palghar Avenue
declared completion Dec 2027 · RLG State Realty Land Developers AND Bui

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.