Mumbai/Project record

MahaRERA · the public record

Raj Residency

Ambernath · Vijay Chahu Patil

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Nov 2026declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for Raj Residency

MahaRERA · P51700054399

Delivery and registration

When is the project declared for completion?

Raj Residency is registered with MahaRERA as P51700054399 and the promoter has declared completion for 30 Nov 2026.

30 Nov 2026

declared completion

1months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP51700054399
Registered on18 Jan 2024
Promoter-declared completion30 Nov 2026
Current statusCertificate Signed
Against today1 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Raj Residency record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 19 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-09-30).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Raj Residency in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Raj Residency Wing A1G+7-
Raj Residency Wing B1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Ambernath, Village Pale, Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by S No 40-2 P, to the south by S No 40-3-2, to the east by S No 40-2P and to the west by S No 40-2P. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambernath

Meera Nanda Bliss
declared completion Nov 2026 · Meera Homes LLP
Precious Empire Wing A, B AND C
declared completion Dec 2026 · RKR Reality
Chaitraban CHS
declared completion Dec 2026 · Annapurna Enterprises
Dipti Skycity Bldg No. 7
declared completion Dec 2026 · Dipti Home Makers Pvt Ltd
Imperial Heights
declared completion Dec 2026 · Krishna Developers
Jai Shriram CO-Operative Housing Society Ltd
declared completion Dec 2026 · Not Available
More builders in Ambernath

Major developers building in Ambernath

More projects in Thane

Other RERA-registered projects in Thane

RAJ Residency
declared completion Dec 2029 · Ruturaj Builders
RAJ Silverstone Phase-2
declared completion Jul 2026 · Skyspace Builtek
RAJ Tattva Phase 1 Commercial
declared completion Dec 2025 · Kothari Autoparts Manufacturers PVT LTD
RAJ Torres Phase 1
declared completion Mar 2019 · Rajesh Estates AND Nirman PVT LTD
Raj Torres Phase II Wing A Wing B Wing C Wing D Wing E
declared completion Mar 2022 · Rajesh Estates AND Nirman PVT LTD
RAJ Ultimate E-Wing
declared completion Dec 2026 · S D U Tradelink PVT Ltd.

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.