Mumbai/Project record

MahaRERA · the public record

RISHABRAJ CLASSIC

MALAD EAST · TRIVENI DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Apr 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for RISHABRAJ CLASSIC

MahaRERA · P51800027149

Delivery and registration

When is the project declared for completion?

RISHABRAJ CLASSIC is registered with MahaRERA as P51800027149 and the promoter has declared completion for 30 Apr 2024.

30 Apr 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800027149
Registered on20 Nov 2020
Promoter-declared completion30 Apr 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RISHABRAJ CLASSIC record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

TRIVENI DEVELOPERS is the promoter of record on 7 projects registered with MahaRERA.

7projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RISHABRAJ CLASSIC in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
RISHABRAJ CLASSIC1G+1031 Oct 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MALAD EAST, TANHAJI NAGAR, Borivali, Mumbai Suburban, 400097. Per the filed land record, the plot is bounded to the north by CTS NO 278A OF VILLAGE KURAR, to the south by CTS NO 278A1 OF VILLAGE KURAR, to the east by EXISTING NALLAH and to the west by 13 MTRS WIDE ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 7 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park9 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)14 km
Lower Parel / Worli business district21 km
Nariman Point / Fort30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad East

Amann Highland Park
declared completion Oct 2026 · MS Relliance Construction CO
Gami And Jaydeep Ventura Commercial Hub
declared completion Oct 2026 · M/S Real Infrastructure CO
Parmar Pearl - JAY Koteshwar Nagar CHS LTD
declared completion Nov 2026 · Parmar Constructions Private Limited
Neelyog Virat -A Wing
declared completion Dec 2026 · Neelyog Construction Pvt Ltd
Royal Pristo
declared completion Dec 2026 · Royal Realtors
Spring Meadows
declared completion Dec 2026 · Renaissance Enterprises
More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Rishabraj Forest Front
declared completion Dec 2028 · Rishabraj Estate Developers PVT LTD
Rishabraj Percy
declared completion Dec 2025 · H Rishabraj Realty
Rishabraj Phoenix
declared completion Feb 2027 · Rishabraj Estate Developers PVT LTD
Rishabraj Pooja
declared completion Dec 2029 · Rishabraj Estate LLP
Rishabraj Trident
declared completion Aug 2028 · H Rishabraj Realty
Rita Tower
declared completion Dec 2024 · K K Krishnan Construction Company PVT LT

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.