Mumbai/Project record

MahaRERA · the public record

S M ROYAL AVENUE

SECTOR 23, TALOJA · SHREEJI DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Dec 2023declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

Free project details

Registration read 19 Jul 2026

RERA details for S M ROYAL AVENUE

MahaRERA · P52000023995

Delivery and registration

When is the project declared for completion?

S M ROYAL AVENUE is registered with MahaRERA as P52000023995 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP52000023995
Registered on14 Jan 2020
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Promoter record

What else is this promoter on record for?

SHREEJI DEVELOPERS is the promoter of record on 27 projects registered with MahaRERA.

27projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 19 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for S M ROYAL AVENUE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
S M ROYAL AVENUE1G+731 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at SECTOR 23, TALOJA, PLOT NO 10, Panvel, Raigarh, 410208. Per the filed land record, the plot is bounded to the north by 11 MTR ROAD, to the south by PLOT NO 31 TO 40, to the east by PLOT NO 11 and to the west by PLOT NO 09. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Shreeji Developers project & its RERA track record →

Other RERA-registered projects in Taloja

Om Unnati
declared completion Nov 2026 · Om Group
Arihant Amisha Phase II
declared completion Dec 2026 · Arihant Aashiyana Private Limited
Arihant Anant
declared completion Dec 2026 · Mahalaxmi Cotton Mills
Orchid Enclave
declared completion Dec 2026 · Siddhivinayak Associates
SAI Suncity Commercial
declared completion Dec 2026 · Chariot Properties LLP
Sarvam
declared completion Dec 2026 · Ashtvinayak Homes
More projects in Raigarh

Other RERA-registered projects in Raigarh

S M SAI
declared completion Jun 2024 · S M Hitech
S R Hari OM
declared completion Dec 2027 · Shree Ganesh Infra
S R Park
declared completion May 2023 · S R Builders & Developers
S R Villa
declared completion May 2022 · S R Builders & Developers
Saavi Empire
declared completion Dec 2027 · Not Available
Saavi Residency
declared completion May 2028 · Not Available

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.