Mumbai/Project record

MahaRERA · the public record

SAFALYA

Mumbai Suburban · VIJAY MALLYA

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Sep 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for SAFALYA

MahaRERA · P51800004580

Delivery and registration

When is the project declared for completion?

SAFALYA is registered with MahaRERA as P51800004580 and the promoter has declared completion for 30 Sep 2022.

30 Sep 2022

declared completion

49months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800004580
Registered on09 Aug 2017
Promoter-declared completion30 Sep 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAFALYA record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

VIJAY MALLYA is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAFALYA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
SAFALYA1G+9-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for SAFALYA, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000014106427/09/2019VEENA VIVEK DESAI vs VIJAYA S MALLYAorder passed
CC00600000019512518/12/2020Mr. Lalit Jeevan Pawaskar and Dr. Jeevan Jagannath Pawaskar vs Mr. Vijay S. Mallyaorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2022Hospitalisation of the Promoter, Mr Vijay Shridhar Mallya, on account of severe illness led to a loss of business and inability to generate funds for the completion of the Project

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400058. Per the filed land record, the plot is bounded to the north by LAND BEARING CTS NO 129 AND 131, to the south by 2nd ROAD PANDURANG WADI, to the east by LAND BEARING CTS NO 134 AND 133 and to the west by LAND BEARING CTS NO 127 AND 129. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 3 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ3 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park7 km
Bandra Kurla Complex (BKC)8 km
Lower Parel / Worli business district14 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri West

Vivan Homes
declared completion Dec 2026 · Imprint Estates Pvt Ltd
Alpine Primo
Registration suspended · declared completion Dec 2026 · Alpine Infraheights LLP
Bella Casa
declared completion Dec 2026 · Konark Bella Casa LLP
Hetali Sagar
declared completion Dec 2026 · Jayesh Himatlal Pandya
La Alteza
declared completion Dec 2026 · Emerald Developers
Mobin Heights
declared completion Dec 2026 · Gahlot Development Services Pvt. Ltd.
More builders in Andheri West

Major developers building in Andheri West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Sagar Manthan
declared completion Sep 2027 · Bhoomi Associates
Sagar Sangeet CHS Adityaraj Paradise
declared completion Dec 2026 · Adityaraj Housing Developers
SAH Parishram CHS Ltd
declared completion Jan 2022 · Shree Raghvanshi Developer
Sahakar Avenue
declared completion Jun 2026 · Sahakar Corporation
Sahakar Bhavan CHS
declared completion Dec 2018 · Subhash Velji Chawda
Sahakar Excel Acropolis - I
declared completion Mar 2028 · Excel Enterprises Realty LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.