Mumbai/Project record

MahaRERA · the public record

SARTHAK HEIGHTS

Andheri West · Sarthak Developers

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Dec 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for SARTHAK HEIGHTS

MahaRERA · P51800007127

Delivery and registration

When is the project declared for completion?

SARTHAK HEIGHTS is registered with MahaRERA as P51800007127 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

10months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800007127
Registered on17 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Promoter record

What else is this promoter on record for?

Sarthak Developers is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SARTHAK HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
SARTHAK HEIGHTS WING B1G+17-
SARTHAK HEIGHTS WING A1G+3-

Legal and disputes

What disputes are disclosed?

9 complaints are on the MahaRERA record for SARTHAK HEIGHTS, with orders passed in 9 of them.

9complaints

9with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005644506/10/2018Imtiaz Doctor vs Sarthak Developersorder passed
CC00600000005644806/10/2018Suleman Hooda vs Sarthak Developersorder passed
CC00600000005644906/10/2018Shanaz Ayub vs Sarthak Developersorder passed
CC00600000005704529/11/2018Imran Kasam Shaikh vs Sarthak Developersorder passed
CC00600000007849015/03/2019Mr Manish and MrsMandeera Chaudhary vs Sarthak Developersorder passed
CC00600000007849315/03/2019Mr Venkatesh and Nimmi Iyer vs Sarthak Developersorder passed
CC00600000007849415/03/2019Percy and Sonia Vasunia vs Sartak Developersorder passed
CC00600000008955201/06/2019Maryam Musaddik Peshimam Nee and vs Sarthak Developersorder passed
CC00600000009016216/07/2019Mr.Mohidin Adhima Siddiq vs Sarthak Developersorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Filed descriptions (status fields empty): 1 “PENDING”. These are the promoter's filed statements, not a current court check. A disposed application or motion does not establish that the whole case is closed. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your unit. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil648/20142014Status not supplied
Filed description: PENDING

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Nov 20191) Administrative delay of nearly 4 years on part of the Municipal Corporation of Greater Mumbai (“MCGM”) to issue part occupation certificate in respect of the commercial premises
30 Nov 201931 Dec 2021On-going litigation with members of the Society and purchasers due to delays in completion of the project which led to a Court Receiver, High Court, Bombay being appointed as Recei
31 Dec 202131 Dec 2025We refer to the subject matter and hereunder submit our application for seeking extension of time for completion of the Project as required under Section 6 of The Real Estate (Regu

Location, Land & Connectivity

Located at Andheri West, Andheri, Mumbai Suburban, 400058. Per the filed land record, the plot is bounded to the north by DP ROAD OF CTS NO 1231-8, to the south by CTS NO 1231-10, to the east by INTERNAL ACCESS ROAD and to the west by CTS NO 1231-11 1238 AND 1244-4. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 4 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport5 km
Bandra Kurla Complex (BKC)8 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri West

Vivan Homes
declared completion Dec 2026 · Imprint Estates Pvt Ltd
Alpine Primo
Registration suspended · declared completion Dec 2026 · Alpine Infraheights LLP
Bella Casa
declared completion Dec 2026 · Konark Bella Casa LLP
Hetali Sagar
declared completion Dec 2026 · Jayesh Himatlal Pandya
La Alteza
declared completion Dec 2026 · Emerald Developers
Mobin Heights
declared completion Dec 2026 · Gahlot Development Services Pvt. Ltd.
More builders in Andheri West

Major developers building in Andheri West

More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Sarvasya
declared completion Mar 2026 · Maverick Realtors
Sarvesh ONE
declared completion Dec 2026 · Sarvesh Urban Developers Private Limited
Sarvodaya Heights
declared completion Sep 2026 · CMG Enterprises
Sarvodaya Pride
declared completion Dec 2026 · Jyotiraditya Realtors AND Developers LLP
Sarvonnati CHS LTD
declared completion Dec 2026 · JAI Enterprises
Sarwarji Heights
declared completion Dec 2026 · Stans Buildtech Shelcon

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.