Mumbai/Project record

MahaRERA · the public record

SHIVTEJ ASHIYANA

Nerul · YOGESH RAMDAS SARJINE

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

15units filed as unsoldInventory · 22 October 2026
31 Dec 2025declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 18 Jul 2026

RERA details for SHIVTEJ ASHIYANA

MahaRERA · P51700011753

Delivery and registration

When is the project declared for completion?

SHIVTEJ ASHIYANA is registered with MahaRERA as P51700011753 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

10months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51700011753
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHIVTEJ ASHIYANA record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Promoter record

What else is this promoter on record for?

YOGESH RAMDAS SARJINE is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

What the filings record, unit by unit

Read from MahaRERA on 22 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 13 units carry one, and 15 of the 28 are recorded unsold.

Here is one unit filed as unsold, beside the amounts filed for comparable units:

UnitCarpetFiled comparisonBased on
103441 sqftRs 47.80 lakh typical, over Rs 47.00 lakh to Rs 59.00 lakh4 filed · number pattern + area (within 2%), same building

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In SHIVTEJ ASHIYANA, 7 of the 15 unsold units have filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See the other 14 units — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SHIVTEJ ASHIYANA1G+831 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2019We have already applied for NOC from CIDCO and completion certificate to NMMC Authority, but NOC from CIDCO is still awaited. Hence completion certificate is also not received till
30 Apr 201931 Dec 2020Building Construction is already completed. No Dues Certificate is awaited from CIDCO to submit to NMMC for Occupancy Certificate.
31 Dec 202031 Dec 2025In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r

Location, Land & Connectivity

Located at Nerul, Thane, Thane, 400706. Per the filed land record, the plot is bounded to the north by 9 MT WIDE ROAD, to the south by PLOT NO 106 A, to the east by PLOT NO 105B and to the west by PLOT NO 105. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 20 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Powai / Hiranandani business park20 km
Bandra Kurla Complex (BKC)22 km
Chhatrapati Shivaji Int'l Airport23 km
Andheri MIDC / SEEPZ24 km
Lower Parel / Worli business district25 km
Nariman Point / Fort28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nerul

Shreeji Dios
declared completion Dec 2026 · Shreeji Ventures Nirmaan Private Limited
Infinity Ikon
declared completion Dec 2026 · Emperia Projects
Plan I
declared completion Dec 2026 · M/s. Tescon Plan-I LLP
Regency Palms Phase IV
declared completion Dec 2026 · Regency INC
Sawan Serenity
declared completion Dec 2026 · Shree Sawan Buildcon
THE Domus Prive
declared completion Dec 2026 · Aramus Ventures LLP
More projects in Thane

Other RERA-registered projects in Thane

Shivtirth
declared completion Dec 2027 · Mangalya Reality
Shlok Apartment
declared completion Dec 2025 · Chetan Abhimanyu Patil
Shobhana CO-Operative Housing Society LTD
declared completion Dec 2022 · Padmanabh Developers
Shon Heights
declared completion Dec 2024 · Green Homes Construction Company
Shraddha Peninsula
declared completion Dec 2026 · Padmagriha Heights
Shram Safal CO-Operative Housing Society LTD
declared completion May 2029 · Adeshwar Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.