Pune/Project record

MahaRERA · the public record

ELEGANT RESIDENCY PHASE II

Nigdi · ARIHANT VASTUSHILP PROPCON PRIVATE LIMITED

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

0units filed as unsoldInventory · 19 October 2026
30 Sep 2024declared completionMahaRERA registration · read 18 Jul 2026
63registered unitsMahaRERA registration · read 18 Jul 2026

From another project · Life Republic Atmos Phase II

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Life Republic Atmos Phase II Project Review · first page
First page of the complete sample.

Free project details

Registration read 18 Jul 2026

RERA details for ELEGANT RESIDENCY PHASE II

MahaRERA · P52100009324

Delivery and registration

When is the project declared for completion?

ELEGANT RESIDENCY PHASE II is registered with MahaRERA as P52100009324 and the promoter has declared completion for 30 Sep 2024.

30 Sep 2024

declared completion

25months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100009324
Registered on22 Aug 2017
Promoter-declared completion30 Sep 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Construction

How much construction cost has been reported?

In ELEGANT RESIDENCY PHASE II, ₹23.22 Cr of a declared ₹24.48 Cr estimated project cost is reported as incurred, about 94.9%, as at the last certified filing with MahaRERA.

94.9%

₹23.22 Cr

of ₹24.48 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 18 Jul 2026

Sales

How many are filed as sold or booked?

In ELEGANT RESIDENCY PHASE II, 48 of 48 homes filed with MahaRERA are recorded as sold or booked, about 100%, and 0 are filed as unsold.

100%sold or booked

48 of 48 homes

₹26.11 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹26.11 Cr (about 100%) is recorded as collected and ₹0 as receivable. The registration lists 63 homes; this inventory lists 48. These are separate filed records. Their counts do not match; neither count establishes today's availability.

Source · MahaRERA sold/unsold inventory filing · read 18 Jul 2026

Filed agreement values: across 48 sold or booked entries with usable filed values and areas, the effective carpet rate is ₹6,533/sqft, with eight in ten falling between ₹5,772 and ₹8,807 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 15 not for sale.

What the filings record, home by home

Read from MahaRERA on 19 October 2026

This unit list contains 63 entries; the separate sales summary contains 48. The lists can differ in status coverage and filing date. Use the source date shown with each.

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific home. On this project 48 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is the amount the promoter reported for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

This snapshot marks all homes in ELEGANT RESIDENCY PHASE II as sold or booked. It does not establish current availability. The filed values can still help you compare a quote. The Sales Report lists the 48 sold or booked entries with filed values: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 48 filed sold/booked entries — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 63 homes are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
ELEGANT RESIDENCY PHASE II1G+86331 Mar 2020

Unit mix on the filing: 63 residential.

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for ELEGANT RESIDENCY PHASE II, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000047118026/06/2024Ravi Banwarilal Dhandhania vs Arihant Vastushlip Propcon Pvt Ltd.order passed
CC1240008913/09/2024Kiran Jaykumar Jadhav vs ARIHANT VASTUSHILP PROPCON PRIVATE LIMITEDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2020revised plan for 3 upper floors in process
31 Mar 202031 Mar 2020The said project is 90% complete. Only installation of Lift and construction of Club house remains pending due to severe heart attack suffered by the Director Mr. Vishal Bandewar,
31 Mar 202031 Mar 2024Construction and development work is completed . However we have some inventory to be sold. We need further time to complete the sales, form an Association of Allottess , Handover

Location, Land & Connectivity

Located at Nigdi, Old Mumbai Pune Highway, Haveli, Pune, 411044. Per the filed land record, the plot is bounded to the north by NALA, to the south by 9 MTR WIDE DP ROAD, to the east by SNO 3 HISSA NO 4 and to the west by SNO 3 HISS NO 2. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 9 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park9 km
Baner–Balewadi belt12 km
Pune Int'l Airport (Lohegaon)18 km
Pune Junction / city centre18 km
Kharadi / EON IT Park21 km
Magarpatta / Hadapsar IT23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nigdi Pradhikaran

Aashirwad Homes
declared completion Dec 2026 · Nest Saswad Realty LLP
Paradise Residency
declared completion Dec 2026 · Balaji Developers
Shuban Enclave
declared completion Dec 2026 · Sahyadri Devcon
Vision Vanessa
declared completion Dec 2026 · P4 Group
Swastik Vyom
declared completion Mar 2027 · Swastik Venture
Vijay Skyline
declared completion Mar 2027 · Chaya Realities
More projects in Pune

Other RERA-registered projects in Pune

Element 77
declared completion Dec 2029 · Vikrant Mohan Riswadkar
Element Square
declared completion Dec 2029 · LJM Estates LLP
Elementis ORO
declared completion Dec 2030 · Adi Homes
Elements
declared completion Dec 2029 · Star Pioneers Construction Private Limit
Elena Homes
declared completion Oct 2020 · Kalimata Properties
Eleve 1
declared completion Mar 2029 · Vedant Rising Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.