Sai SparshA3,A4

Kapurhol · Jalan Associates

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2024declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Sai SparshA3,A4

MahaRERA · P52100003340

Delivery and registration

When is the project declared for completion?

Sai SparshA3,A4 is registered with MahaRERA as P52100003340 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100003340
Registered on05 Aug 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sai SparshA3,A4 record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

Jalan Associates is the promoter of record on 2 projects registered with MahaRERA.

2projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sai SparshA3,A4 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
A31G+531 Dec 2021
A41G+531 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2021Previous sanction for the Project was for 3 floors which are completed. New sanctioned plan was received on 21/10/2020 from PMRDA for the 4th floor of the building (Delayed due to
31 Dec 202130 Jun 2024We M/s Jalan Associates having project named as Sai Sparsh A3, A4. Project Registration No. P52100003340 situated at Gat No. 9/1 at Kapurhol, Taluka Bhor, District Pune 412205 do h

Location, Land & Connectivity

Located at Kapurhol, Pune Satara Highway, Bhor, Pune, 412205. Per the filed land record, the plot is bounded to the north by Gat no 9-1 P, to the south by Road, to the east by Road and to the west by Building A2 as per sanctioned layout plan. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 32 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Magarpatta / Hadapsar IT32 km
Pune Junction / city centre33 km
Kharadi / EON IT Park36 km
Pune Int'l Airport (Lohegaon)39 km
Baner–Balewadi belt39 km
Hinjewadi Rajiv Gandhi IT Park44 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kapurhol

Royal Purandar
declared completion Dec 2026 · Carcanet Infra Projects Private Limited
Shree Venkatesh SAI Residency
Not filing quarterly progress reports · declared completion Mar 2027 · Shree Venkatesh SAI Associates
Balaji Dham Phase-1
declared completion Mar 2027 · Garva Land Deal Private Limited
Industree
declared completion Feb 2028 · Dhankawade Square Realtors LLP
Navkar Pleasure
declared completion Dec 2028 · Parag Properties
Pooja Heavan Park
declared completion Dec 2028 · Pooja Developers
More projects in Pune

Other RERA-registered projects in Pune

SAI Square
declared completion Aug 2025 · SAI Square
SAI Srushti
declared completion Dec 2027 · Ashok Nirman Developers
SAI Stella
declared completion Dec 2028 · M/s.shree Sai Capstone
SAI Suman
declared completion Dec 2021 · Sunsai Developers
SAI Sundaram
declared completion Oct 2018 · Gurusai Developers
Sai Sushrut
declared completion Dec 2027 · SAI Sushrut Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.