Pune/Project record

MahaRERA · the public record

SAMRAJYA

Pimpale Gurav · GARVE PATIL CONSTRUCTION COMPANY

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2023declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for SAMRAJYA

MahaRERA · P52100014056

Delivery and registration

When is the project declared for completion?

SAMRAJYA is registered with MahaRERA as P52100014056 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

40months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100014056
Registered on07 Nov 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 40 months past the declared date

Promoter record

What else is this promoter on record for?

GARVE PATIL CONSTRUCTION COMPANY is the promoter of record on 4 projects registered with MahaRERA.

4projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAMRAJYA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
D WING1G+931 Dec 2019
E WING1G+731 Dec 2019
F WING1G+731 Dec 2019

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SAMRAJYA, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000006444220/10/2020PRAFULLACHANDRA KHADE vs Shri Gangarde Associatesorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020Project is almost completed. Out of 3 buildings 2 are already completed and remaining one is almost on completion at 70% which will be completed in due time. Hence we request you
30 Dec 202030 Jun 2022To Maharashtra Real Estate Regulatory Authority, 6th & 7th Floor, Housefin Bhavan, Plot No. C - 21, E - Block, Bandra Kurla Complex, Bandra (E), Mumbai 400051. Subject:-
30 Jun 202230 Jun 2023To Maharashtra Real Estate Regulatory Authority, 6th & 7th Floor, Housefin Bhavan, Plot No. C - 21, E - Block, Bandra Kurla Complex, Bandra (E), Mumbai 400051 Subject:- Ex

Location, Land & Connectivity

Located at Pimpale Gurav, Pimpale Gurav, Haveli, Pune, 411061. Per the filed land record, the plot is bounded to the north by ROAD AND CTS NO 1038, to the south by REMAINING PROPERTY, to the east by CTS NO 1032 and to the west by CTS NO 1088. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 128 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park128 km
Baner–Balewadi belt134 km
Pune Junction / city centre144 km
Pune Int'l Airport (Lohegaon)144 km
Kharadi / EON IT Park147 km
Magarpatta / Hadapsar IT149 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pimple Gurav

Dwarkadhish Apartment
declared completion Oct 2026 · Vishal Pravin Tank
Krishna Prabha Aangan
declared completion Nov 2026 · Rathod AND Sons
1 Priority Rathod Business Zone
declared completion Dec 2026 · Shreeji Developers
Eastern River Residency Wing D
declared completion Dec 2026 · Not Available
Akshay Vista
declared completion May 2027 · Akshay Skyscrapers Private Limited
7 Avenue
declared completion Feb 2028 · Destiny Developers
More projects in Pune

Other RERA-registered projects in Pune

Samrajya B Wing
declared completion Dec 2031 · Garve Patil Construction Company
Samrajya C Wing
declared completion Dec 2028 · Garve Patil Construction Company
Samrajya Wing GH
declared completion Dec 2029 · Garve Patil Construction Company
Samruddhi
declared completion Mar 2018 · Kunda Ramachandra Chinchanikar
Samruddhi
declared completion Dec 2021 · Shree Dolasnath Associates
Samruddhi
declared completion Dec 2024 · Raahi

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.