SIDDHI AVENUE

RAHATNI · FLORET BUILDCON (OPC) PRIVATE LIMITED

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for SIDDHI AVENUE

MahaRERA · P52100027038

Delivery and registration

When is the project declared for completion?

SIDDHI AVENUE is registered with MahaRERA as P52100027038 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

52months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100027038
Registered on10 Nov 2020
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SIDDHI AVENUE record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SIDDHI AVENUE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SIDDHI AVENUE1G+431 Mar 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at RAHATNI, RAHATNI, Pune City, Pune, 411027. Per the filed land record, the plot is bounded to the north by KHULE PLOT, to the south by TRIPATHI PLOT, to the east by BALWADKAR AND WAGH PLOT and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Pimple Nilakh

Sky 2 Cosmos
declared completion Oct 2026 · Emperos Properties
Vimal Twin Tower A Wing
declared completion Oct 2026 · Kate Promoters & Developers
Yashoda Heights
declared completion Nov 2026 · Paras Shivajirao Dhore
THE Benchmark
declared completion Nov 2026 · Shree Samarth Developers
24 Sunshine Viva
declared completion Dec 2026 · Parshwa Developers
ASR Capital
declared completion Dec 2026 · Aceprime Developers LLP
More builders in Pimple Nilakh

Major developers building in Pimple Nilakh

More projects in Pune

Other RERA-registered projects in Pune

Siddhi Avenue
declared completion Dec 2027 · Siddhivinayak Developers
Siddhi-Business BAY
declared completion Dec 2026 · Bhairav Promoters
Siddhi Homes
declared completion May 2022 · Shree Ganesh Developers
Siddhi Homes Phase II
declared completion Jun 2023 · Shree Ganesh Developers
Siddhi Icon
declared completion Jun 2027 · Bhairav S P Associates
Siddhi Nakoda
declared completion Dec 2021 · Bharat Vastimal Solanki

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.