TANISH COMMERCIAL COMPLEX

Pune · JAI BHOLE DEVELOPERS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
31 Jan 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for TANISH COMMERCIAL COMPLEX

MahaRERA · P52100012938

Delivery and registration

When is the project declared for completion?

TANISH COMMERCIAL COMPLEX is registered with MahaRERA as P52100012938 and the promoter has declared completion for 31 Jan 2022.

31 Jan 2022

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100012938
Registered on07 Sep 2017
Promoter-declared completion31 Jan 2022
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for TANISH COMMERCIAL COMPLEX record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.

Promoter record

What else is this promoter on record for?

JAI BHOLE DEVELOPERS is the promoter of record on 4 projects registered with MahaRERA.

4projects

registered with MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 18 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for TANISH COMMERCIAL COMPLEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
TANISH COMMERCIAL COMPLEX1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2020ALL THE WORK HAS BEEN DONE. BUT WE HAVENT RECEIVED THE OC OF THE BUILDING FROM LOCAL AUTHORITY. SO PLEASE EXTEND THE SAME.
31 Jul 202031 Jul 2021Due to Corona Pandemic we weren't able to complete the project in time. Request you to extend the time of completion of Project upto 31/07/2021.

Location, Land & Connectivity

Located at Junnar, Pune, 410504. Per the filed land record, the plot is bounded to the north by ROAD, to the south by INTERNAL ROAD, to the east by INTERNAL ROAD and to the west by 633 PARK. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 127 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park127 km
Baner–Balewadi belt132 km
Pune Int'l Airport (Lohegaon)141 km
Pune Junction / city centre142 km
Kharadi / EON IT Park145 km
Magarpatta / Hadapsar IT147 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Narayangaon

Crystal Tower
declared completion Dec 2026 · Jadhav Civil Project
Divyata Park
declared completion Dec 2026 · Shantaram J Gadhve
Vizion Galaxy D
declared completion Dec 2026 · Vizion Construction
Landmark Paradise
declared completion Jul 2027 · Landmark Promoters & Builders
Prime Vastu
declared completion Jul 2027 · Prime Construction
Gaurinandan Heights
declared completion Dec 2027 · Trident Civil Projects
More projects in Pune

Other RERA-registered projects in Pune

Tanish Dreams A
declared completion Apr 2024 · Tanish Developers
Tanish Dreams B
declared completion Mar 2025 · Tanish Properties
Tanish Dreams C
declared completion Mar 2025 · Girish Naresh Mehta
Tanish Dreams D
declared completion Mar 2025 · Girish Naresh Mehta
Tanish Dreams E
declared completion Feb 2025 · Tanish Properties
Tanish Dreams F
declared completion Apr 2024 · Tanish Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.