VANDAN VIHAR

WADKI · GVN DEVELOPERS PVT LTD

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Jun 2027declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for VANDAN VIHAR

MahaRERA · P52100016206

Delivery and registration

When is the project declared for completion?

VANDAN VIHAR is registered with MahaRERA as P52100016206 and the promoter has declared completion for 30 Jun 2027.

30 Jun 2027

declared completion

8months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP52100016206
Registered on24 Apr 2018
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today8 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VANDAN VIHAR record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VANDAN VIHAR in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
B1G+6-
A1G+4-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for VANDAN VIHAR, with orders passed in 1 of them.

2complaints

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000020820902/02/2023Shubham Santosh More vs Vaibhav Narendra Lodhaorder passed
CC1250129819/04/2025SACHIN BHANUDAS JAGTAP vs GVN DEVELOPERS PVT LTDpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered29 Mar 2024The proposed date of completion was 30/03/2023. But due to changes in UDCPR rules along with waiting period for new sanctioning, we were unable to move forward with our constructio
29 Mar 202430 Jun 2027We will apply for final Fire NOC of Building B to PMRDA, which we expect to get by 30.05.2024. On receiving, we will apply for grant of OCCUPANCY CERTIFICATE to PMRDA, which we exp

Location, Land & Connectivity

Located at WADKI , WADKI NALA ROAD, Pune City, Pune, 412308. Per the filed land record, the plot is bounded to the north by 12MTR ROAD, to the south by GAT NO 1225, to the east by GAT NO 1242 1243 and to the west by GAT NO 1228 1241. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 10 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Magarpatta / Hadapsar IT10 km
Kharadi / EON IT Park13 km
Pune Junction / city centre15 km
Pune Int'l Airport (Lohegaon)17 km
Baner–Balewadi belt25 km
Hinjewadi Rajiv Gandhi IT Park31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Fursungi

Green Hive Plus Wing A4
declared completion Dec 2026 · Ram India Shelters
THE Mpire Building E
declared completion Dec 2026 · AGN Venture
AGS Complex
declared completion Sep 2027 · AGS Properties
Pacific Tower
declared completion Sep 2027 · Chaitanya Developers
Evara
declared completion Dec 2027 · G D Developers
Krushna Heights
declared completion Dec 2027 · Balasaheb Kalu Kamthe
More builders in Fursungi

Major developers building in Fursungi

More projects in Pune

Other RERA-registered projects in Pune

Vande Mataram D Wing
declared completion Dec 2026 · Shree Sai Samarth Developers
Vanessa
declared completion Dec 2026 · P4 Group
Vanity View
declared completion Dec 2026 · RB Developers
Vansh Vastu
declared completion May 2027 · Rajvansh Infra
Vantaara
declared completion Mar 2029 · Reden Realty Buildcon LLP
Vantage Capital
declared completion Mar 2027 · Vinode Wakadkar Infrastructure

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Pune projects.