Ventila Park

Ganeshnagar Bopkhel · Krushnarang Builders

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

0units filed as unsoldInventory · 23 October 2026
30 Nov 2025declared completionMahaRERA registration · read 19 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 19 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 19 Jul 2026

RERA details for Ventila Park

MahaRERA · P52100023794

Delivery and registration

When is the project declared for completion?

Ventila Park is registered with MahaRERA as P52100023794 and the promoter has declared completion for 30 Nov 2025.

30 Nov 2025

declared completion

11months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 19 Jul 2026

MahaRERA registrationP52100023794
Registered on06 Jan 2020
Promoter-declared completion30 Nov 2025
Current statusCertificate Signed
Against todayabout 11 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Ventila Park record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 19 Jul 2026

View the free 14-item checklist →

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

What the filings record, unit by unit

Read from MahaRERA on 23 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 96 units carry one, and Every unit on the filing is recorded sold or booked.

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. Only one observation of this ledger so far: no change can be reported yet.

This snapshot marks all units in Ventila Park as sold or booked. It does not establish current availability. The filed values can still help you compare a quote. The Sales Report lists the 96 sold or booked entries with filed values: each unit, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 96 filed sold/booked entries — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
Building A1G+13-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Ventila Park, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 19 Jul 2026

Complaint no.FiledPartiesStatus
CC1250291820/08/2025Shivam Kumar Singh vs Krushnarang Builderspending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Nov 20251. Project is 95% completed. 2. 51% consent obtained from allottees. 3. Consent for next 5 months only. 4. Form B uploaded in other tab No.1 and in main Application. 5.PERT

Location, Land & Connectivity

Located at Ganeshnagar Bopkhel, Colony no 16 Main road , Haveli, Pune, 411031. Per the filed land record, the plot is bounded to the north by 6M wide proposed road, to the south by 18m wide DP road, to the east by 12M wide DP road and to the west by Transformer area. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 159 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)158 km
Kharadi / EON IT Park159 km
Magarpatta / Hadapsar IT162 km
Pune Junction / city centre166 km
Baner–Balewadi belt172 km
Hinjewadi Rajiv Gandhi IT Park174 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bopkhel

Swami Shrushti
declared completion Dec 2026 · Pruthviraj Developers Through Sagar Hanu
Crystal Space
declared completion Mar 2027 · SAI Samarth Developers
Kundan Praangan
declared completion Mar 2027 · Kundan AND Jain Developers LLP
Aksha Casa Palladium
declared completion May 2027 · Accurate Realities
Abhang Recidency
declared completion Jun 2027 · SAI Developers
Casa Millennium
declared completion Dec 2027 · G P Associates
More projects in Pune

Other RERA-registered projects in Pune

Venture City B AND C Wing
declared completion Jun 2026 · Venture Group
Venu Tower
declared completion Mar 2026 · Vighnaharta Developers
Venus Enclave
declared completion Dec 2025 · K P Abdul Rehman Ramees
Verdant 84
declared completion Dec 2025 · Verdant Realty
Veridian Park
declared completion Dec 2028 · Platinum Builders
Verista
declared completion May 2025 · VM Real Tech LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.