RERA Property Intelligence Report · Preview

CHURCHGATE PALACE

ICARE BUILDERS & DEVELOPERS · · K-RERA PRM/KA/RERA/1257/333/PR/180217/001365

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
2
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

60
Registered units
₹8.0 Cr
Est. construction cost
Units profiled
20
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units60Total inventory registered with K-RERA.
Registered land area2,104 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings1Official tower/wing count in the K-RERA detail page.
Parking disclosed60 total (0 open) — 1.00 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date31-10-2016

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
CHURCHGATE PALACE56060-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 60 official flat/unit rows, matching the 60 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK45892.0-1,014.0 sqft1.6-1.9 sqft45
1BHK10610.0-645.0 sqft1.1-1.2 sqft10
3BHK51,130.0 sqft2.1 sqft5

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
CHURCHGATE PALACE60610.0-1,130.0 sqft1.1-2.1 sqft60
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G01CHURCHGATE PALACE13BHK1,130.0 sqft2.1 sqft1
G02CHURCHGATE PALACE12BHK995.0 sqft1.8 sqft1
G03CHURCHGATE PALACE12BHK955.0 sqft1.7 sqft1
G04CHURCHGATE PALACE11BHK645.0 sqft1.2 sqft1
G05CHURCHGATE PALACE12BHK892.0 sqft1.6 sqft1
G06CHURCHGATE PALACE12BHK1,014.0 sqft1.9 sqft1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~912 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a boutique, low-density project — 60 homes across 1 tower. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 60 parking spaces for 60 homes (~1.0 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~2 sqft per home; across all 60 homes that is ~0% of the plot — on the lower side — the undivided shares sum to noticeably less than the plot, worth asking the builder why before relying on it. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

2 of 16 compliance document slots are filed as Not Applicable; the remaining 14 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Oct 2019, extended (Section 6 Extension) to 30 Apr 2021 — both dates have passed with no OC on file. The extension on file was granted on 19 Feb 2021 (K-RERA extension no. EX/PRM/KA/RERA/1257/333/PR/210219/001365) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectVEERENDRA SHETTIGAR-2004CITY LIGHT BUILDING, MOODBIDRI
ContractorICARE BUILDERS & DEVELOPERES-2009PALACE ENCLAVE, MOODBIDRI
Structural engineerANAND BHAT---

Builder track record

RERA filing

Icare Builders has 2 other K-RERA-registered projects in our records (average reported construction progress 50%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹13.3 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: SYNDICATE BANK MOODBIDRI (IFSC SYNB0000128, a/c …3071). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Outer Ring Road / Manyata10 km
Kempegowda Int'l Airport11 km
MG Road / city centre18 km
Whitefield IT hub22 km
Bellandur–Marathahalli belt23 km
Electronic City32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Icare Builders.
Icare Builders has 3 projects registered in Bangalore.

Other projects by this builder in Bangalore

Icare Bell Street Palace
Filing overdue · 25% built · 10% sold
Icare City Mall
Filing overdue · 75% built · 9% sold

Other RERA-registered projects in Sathnur Village

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Churchgate Palace?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 16 Jul 2026