Bangalore/Project record

K-RERA · the public record

DYNASTY II

· MOHTISHAM COMPLEXES

Is this the right project?
Which unit should you choose?

Read the free RERA facts below. For help choosing a unit or comparing a price, select a report.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
73%construction reportedQ4 2025 filing
87units not bookedof 106 · Q4 2025 filing
0registered unitsK-RERA registration · read 16 Jul 2026

Free project details

Registration read 16 Jul 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q4 2025

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

Registered units and project size

RESIDENTIAL APARTMENTS
106

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

1.9registered acres

0.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for DYNASTY II

K-RERA · PRM/KA/RERA/1257/334/PR/030625/007804

Project facts and comparisons

On the register

Land area7,487 sq m (1.9 acres)
Tower/wing entries1
Unit mix106 × RESIDENTIAL APARTMENTS

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Official carpet area6,989 sqmTotal carpet area reported for the project.
Official built-up area10,376 sqmUseful scale context when comparing density and project cost.
Registered land area7,487 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.208Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)88Separate filed counts; these categories may overlap and are not added together.
Covered-parking field64Separate filed counts; these categories may overlap and are not added together.
Open-parking field8Separate filed counts; these categories may overlap and are not added together.
Garage field28Separate filed counts; these categories may overlap and are not added together.
Approved plan numberPlanUse this to match the sanctioned drawing set shown by the builder.
Plan approval date19-07-2024
Project start date01-02-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
RESIDENTIAL APARTMENTS106100%6,989 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
DYNASTY II141068838.6 m

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

All 5 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

See the filed approval statuses and linked documents →

Complaints on this project's K-RERA page (1 complaint listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/201009/0006789
09-10-2020
CompensationCANOPY (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

4 of 4 applicable approvals are marked Approved in the filing. Check the linked documents for their scope and validity.

6 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
KSPCB- PCB (10 Acres to 125 Acres)Approved23-02-2024CFE.pdf
KPTCL- BESCOMApproved26-12-2024ANNEXURE 95 Dynasty II NOC - MESCOM.pdf
Fire and SafetyApproved28-03-2022ANNEXURE 99 FIRE NOC.pdf
Labour and Education DepartmentApproved23-01-2025Labour License.pdf

Builder track record

RERA filing

Mohtisham Complexes has 4 other K-RERA-registered projects in our records (average reported construction progress 78%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹4.16 Cr collected from buyers, ₹29.45 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹29.45 Cr) exceeded buyer collections (₹4.16 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress69% → 73% (+4 pts)
Units sold/booked as registered19/106 (18%)
Buyer collections in available QPRs₹5.69 Cr
Escrow withdrawals in available QPRs₹30.67 Cr (5.39x collections)
  • Construction progress moved from 69% to 73% across the filed QPR window.
  • Across available QPR rows, escrow withdrawals are 5.39x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Branch : IFSC Code : Pin Code : IFSC Code : Pin Code :. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 10 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
MG Road / city centre3 km
Outer Ring Road / Manyata10 km
Bellandur–Marathahalli belt12 km
Electronic City16 km
Whitefield IT hub19 km
Kempegowda Int'l Airport30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Mohtisham Complexes. View Mohtisham Complexes's full track record →
Mohtisham Complexes has 5 projects registered in Bangalore, 1 completed.
1 complaints on the K-RERA register against Mohtisham Complexes in Bangalore.

Other projects by this builder in Bangalore

Amity
Filing overdue · 100% built · 82% sold
Lucent
Filing overdue · 55% built · 42% sold

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 16 Jul 2026. Document and inventory dates are shown in their sections.