Bangalore/Project record

K-RERA · the public record

HIMAGIRI AVENUE

Anekal · B RAMA DEVI

Project Review · example purchase

Spending a few crores on a plot? ₹4,999 to check what you’re buying.

Check what the plans put beside your plot, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best plots.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
100%construction reportedQ4 2025 filing
01 Mar 2025declared completionK-RERA registration · read 26 Oct 2026

Free project details

Registration read 26 Oct 2026

Construction progress and dates

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q4 2025

declared completion

01 Mar 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 26 Oct 2026

Registered units and project size

Odd Sites Plots
77

Filed categories, unchanged · K-RERA registration · read 26 Oct 2026

The whole registration

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for HIMAGIRI AVENUE

K-RERA · PRM/KA/RERA/1251/308/PR/260523/005949

Project facts and comparisons

On the register

Declared completion1 March 2025
Unit mix77 × Odd Sites Plots

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Approved plan numberSTRRPA/TP/LAO/20/2021-22Use this to match the sanctioned drawing set shown by the builder.
Plan approval date04-06-2022
Project start date01-03-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Odd Sites Plots77100%12,824 sqm

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

The promoter answered No to the land-litigation question. This is a filed declaration, not a court search.

7 of 28 compliance document slots are filed as Not Applicable; the remaining 21 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 01 Mar 2025, extended (an extension) to 01 Mar 2026 — both dates have passed with no OC on file. An extension application filed on 28 Feb 2025 is pending with K-RERA — until it is approved, the registration stands lapsed.

See the filed approval statuses and linked documents →

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Statutory approval status

RERA filing

2 of 2 applicable approvals are marked Approved in the filing. Check the linked documents for their scope and validity.

9 further authority slots are marked not applicable in the filing.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved10-11-2022Water Noc with fee Declaration.pdf
KPTCL- BESCOMApproved09-12-2022BESCOM Noc with fee receipt.pdf

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantLakshmi G K2348202017Bengaluru Urban, Karnataka - 560078
EngineerS CHANDRASHEKARBCC/BL-3.6/E-0070/21-222021Bengaluru Urban, Karnataka - 560003

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress95% → 100% (+5 pts)
  • Construction progress moved from 95% to 100% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Karnataka Bank Ltd. SARAKKI LAYOUT IFSC Code : KARB0000098 Pin Code : 560078. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest of the listed job hubs is about 15 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Electronic City15 km
Bellandur–Marathahalli belt20 km
Whitefield IT hub21 km
MG Road / city centre29 km
Outer Ring Road / Manyata34 km
Kempegowda Int'l Airport47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Rama Devi.
Rama Devi has 2 projects registered in Bangalore, 2 completed.

Other projects by this builder in Bangalore

Himagiri Vista
Filing overdue · 100% built

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 26 Oct 2026. Document and inventory dates are shown in their sections.