Bangalore/Project record

K-RERA · the public record

WHITE LOTUS OHANA

Bengaluru North · WHITE LOTUS LIFESCAPES

Project Review · example purchase

Spending a few crores on a home? ₹4,999 to check what you’re buying.

Check what the plans put beside your home, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

From another project · Prestige Park Grove

Avoid bad decisions, only go for the best homes.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
Prestige Park Grove Project Review · first page
First page of the complete sample.
30 Apr 2022declared completionK-RERA registration · read 25 Oct 2026
15registered unitsK-RERA registration · read 25 Oct 2026

Free project details

Registration read 25 Oct 2026

Registered units and project size

APARTMENT
7

Filed categories, unchanged · K-RERA registration · read 25 Oct 2026

The whole registration

0.3registered acres

45.1registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual unit.

RERA details for WHITE LOTUS OHANA

K-RERA · PRM/KA/RERA/1251/309/PR/190809/002762

Project facts and comparisons

On the register

Declared completion30 April 2022
Land area1,347 sq m (0.3 acres)
Homes registered15
Tower/wing entries1
Unit mix7 × APARTMENT

In context

Density45.1 homes per acre
Density in context20th percentile of 529 Bengaluru North projects (median 75.3)

Source: K-RERA. Each comparison names the group of projects used.

Project areas, parking and inventory

Project areas and parking

RERA filing
DisclosureOfficial valueWhy it matters
Registered units15Total inventory registered with K-RERA.
Official carpet area940 sqmTotal carpet area reported for the project.
Registered land area1,347 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)30Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date15-04-2019

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
APARTMENT7100%940 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
White Lotus OHANA71530-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 15 official flat/unit rows, matching the 15 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK15129.9-135.7 sqm71.9-92.9 sqm30

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
White Lotus OHANA15129.9-135.7 sqm71.9-92.9 sqm30
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1White Lotus OHANA03BHK129.9 sqm71.9 sqm2
101White Lotus OHANA13BHK132.2 sqm86.0 sqm2
102White Lotus OHANA13BHK130.0 sqm86.0 sqm2
201White Lotus OHANA23BHK135.7 sqm92.9 sqm2
202White Lotus OHANA23BHK133.5 sqm90.9 sqm2
301White Lotus OHANA33BHK135.7 sqm92.9 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

Litigation status was not supplied in the captured record. This is not confirmation that there are no cases.

All 22 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Apr 2022, extended (Section 6 Extension) to 30 Jan 2024 — both dates have passed with no OC on file. The extension on file was granted on 18 Jul 2023 (K-RERA extension no. EX/PRM/KA/RERA/1251/309/PR/230718/002762) — it has been used, its deadline has also passed, and no further extension is recorded.

Approval documents

Electricity (BESCOM/ESCOM)Document listed: BESCOM
Water & sewage (BWSSB/KWSSB)Document listed: BWSSB
Fire NOCNot identified in the document list
Pollution control (KSPCB)Document listed: KSPCB
Environmental clearanceNot identified in the document list
Airport Authority height clearanceDocument listed: Airport Authority of India

A listed file does not confirm approval. An unlisted file does not establish that an approval is missing or required. Check the documents and their applicability before relying on them.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Architect1 LeapingFrog Studio-20133rd Cross, Domlur Layout
Structural engineerRajesh Consultants---

Builder track record

RERA filing

White Lotus has 4 other K-RERA-registered projects in our records (average reported construction progress 15%). 3 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹124.0 lakhs per unit — the developer's own declared construction/development cost, not a unit agreement or asking price. This project-cost average cannot establish whether a quoted unit price is fair. Compare the exact unit, area basis, date and included charges in any price evidence.

RERA 70% project account is on file: HDFC Richmond Road (IFSC HDFC0000523, a/c …2231). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest of the listed job hubs is about 9 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
MG Road / city centre1 km
Outer Ring Road / Manyata9 km
Bellandur–Marathahalli belt9 km
Electronic City15 km
Whitefield IT hub16 km
Kempegowda Int'l Airport28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by White Lotus. View White Lotus's full track record →
White Lotus has 5 projects registered in Bangalore.

Other projects by this builder in Bangalore

White Lotus Amanvana
Filing overdue · 15% built · 11% sold
White Lotus Kalpavriksha
No filings

Other RERA-registered projects in Ashok Nagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.