At Bellanza in Mulund West, choosing between Wings A–C and Wings D–F changes the stated possession month from December 2026 to June 2027. The promoter remains PRESTIGE MULUND REALTY PRIVATE LIMITED, according to the individual MahaRERA project records identified below. A family choosing a flat within the same development is also choosing between different stated moving timelines.

Compare the registered phase before settling on the development. That is the practical lesson from these Mumbai project filings. A familiar name can bring a home onto a shortlist. The particular wing determines which dated commitment belongs beside its price.

The question of developer identity has acquired fresh relevance. Maharashtra has barred society managing committee members, office-bearers and their relatives from acting as developers in society redevelopment, according to Hindustan Times. For a homebuyer, the useful habit is to carry that attention to identity into the project comparison: establish the named promoter, then connect the proposed flat to its registered phase and stated possession date.

The projects below illustrate that comparison across Mumbai locations. They are not presented as a list of society redevelopment schemes or as examples of the reported restriction’s application.

Where the dates separate

The individual MahaRERA project records for Bellanza, Prestige Ocean Towers and Bhagwati Elysia identify the following promoters, recorded statuses and stated possession months. The registration column identifies the exact project record supporting each entry.

Project Registered promoter Registration number Recorded status Stated possession
Bellanza Phase 1 — Wings A–C at The Prestige CityPRESTIGE MULUND REALTY PRIVATE LIMITEDP51800045339Under constructionDecember 2026
Bellanza Phase 2 — Wings D–F at The Prestige CityPRESTIGE MULUND REALTY PRIVATE LIMITEDP51800046488Under constructionJune 2027
Prestige Ocean Towers — NorthPrestige Projects Private LimitedP51900053993Under constructionJune 2030
Prestige Ocean Towers — SouthPrestige Projects Private LimitedP51900066470Under constructionDecember 2030
Bhagwati Elysia IIIBHAGWATI SIGNATURE LLPP52000056158Under constructionDecember 2029
Bhagwati Elysia IVBHAGWATI SIGNATURE LLPP52000056049Under constructionDecember 2029

For a household considering Mulund West, Bellanza’s phase distinction belongs in the first discussion about affordability. A later planned move can change how long the family expects to keep its present accommodation and when it wants to arrange a school change. Those household choices deserve attention alongside carpet area and layout.

At Prestige Ocean Towers in Bhuleshwar, the distinguishing words are North and South. Writing only the development name and possession year would erase the difference between June and December. The same named promoter appears against each registration, but the stated month remains specific to the tower.

These are comparisons of stated possession dates and registration history; neither establishes physical completion, available homes or a verified handover date.

Panvel shows why phase names need reading

The registration history adds a revealing detail. Bhagwati Elysia IV was registered before Bhagwati Elysia III, according to the MahaRERA registration entries identified in the table. Their registration dates are 6 days apart. The Roman numerals run in a different order from the registration sequence.

For someone comparing homes in Panvel, this removes a tempting shortcut. Reading the phase number as a sequence of registration or planned possession would give the wrong impression. Here, the matching possession month lets the household compare layouts and payment schedules without assuming a timing difference between the phases.

Quietlist’s calculation from the project-specific possession dates shows a 6-month separation within both the Bellanza and Prestige Ocean Towers pairs. Bhagwati Elysia supplies the counterexample. Separate registrations make the comparison necessary; they do not predetermine its answer.

The practical consequence is straightforward. Keep each phase on its own line when comparing homes. Record the promoter in full, even where the same company appears again. Put the stated possession month beside the flat being discussed. This preserves useful distinctions as a shortlist passes between family members, sales teams and advisers.

Follow the date down to the building

MahaRERA’s Guidance for Home Buyers treats researching a property and checking its progress as separate steps. That separation helps organise the next conversation after comparing dates.

Begin with identity. Ask the sales team to connect the proposed flat, its wing and the complete project name to the relevant registration. Keep the named promoter beside that entry. Subsequent documents should be matched to that same home.

Then examine the stated deadline. MahaRERA’s guidance on quarterly and annual project updates directs promoters to update building-wise completion dates. It specifies that a building’s date cannot extend beyond the revised proposed project completion date. The building therefore deserves attention even after the correct registration has been found.

Applied to a Bellanza enquiry, that means asking which building entry covers the proposed wing. At Ocean Towers, it means retaining North or South throughout the discussion. Ask to see the building-wise date alongside the project date and how the stated possession month relates to them.

Finally, request the corresponding building’s dated progress filing. Read its reporting period before interpreting the work described. Keep that document beside the possession date in the household’s notes, with each clearly labelled.

Mumbai’s redevelopment discussion puts attention on who will build. The homebuyer can carry that question further: which company, which registered phase, which building and which stated date? Keeping those details together turns a familiar project name into a specific home a family can assess—and plan around.