Developer RERA record

Ameya Commercial

Ameya Commercial has 10 RERA-registered projects: weak Gurugram delivery record (0/5 projects with OC); 7 projects past their declared completion date. All figures are the developer's own regulator filings.

7
Past declared date
0/5
Gurugram with OC
28
RERA complaints filed

Public registration records

These records have not been classified as delivered, under construction or overdue. The declared date and status are filings, not a current site inspection.

AMEYA SHINE

Hyderabad region · Registered: 2023-09-06 · Declared completion: 2026-04-25

AMEYA RISE

Hyderabad region · Registered: 2023-09-12 · Declared completion: 2026-04-25

Considering a specific Ameya Commercial project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (7)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
Aprameya PrasiddhiBengaluru2018-03
Supratheekam By AprameyaBengaluru2023-09
APRAMEYA BRINDAVANAM ELITEBengaluru2022-10
COMMERCIAL COLONYGurugram2026-02
COMMERCIAL COLONYGurugram2024-08
SAPPHIRE57Gurugram2026-04
SAPPHIRE 82AGurugram2026-04
Registered, no progress filed yet (1)click to expand
ProjectCity
SAPPHIRE 84Gurugram

RERA complaints & orders

Regulatory record

28 total complaints filed — above average for builders we track (61th percentile).

28
MahaRERA complaints

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Figures are Ameya Commercial's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.