Developer RERA record

Ansal

Ansal has 34 RERA-registered projects: weak Gurugram delivery record (0/1 projects with OC); 28 projects past their declared completion date. All figures are the developer's own regulator filings.

28
Past declared date
0/1
Gurugram with OC
28
RERA complaints filed

Public registration records

These records have not been classified as delivered, under construction or overdue. The declared date and status are filings, not a current site inspection.

Considering a specific Ansal project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (28)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
ANSAL HUB 83 BOULEVARDGurugram2020-12
PLOT ZONE I (3B, 4A, 4B) (Default on QPR)Noida2021-04
PLOT ZONE V (1B) (Default on QPR)Noida2026-02
PLOT ZONE IV(5,6,1A) (Default on QPR)Noida2024-08
PLOT ZONE III(2A,2B) (Default on QPR)Noida2024-08
PLOT ZONE II (3A 3C 4C) (Default on QPR)Noida2021-04
FAIRWAY ZONE-3 (TOWER E & L) (Default on QPR)Noida2019-12
PARADISE CRYSTAL ZONE I (N&O) (Default on QPR)Noida2021-09
SUSHANT SERENE RESIDENCY PHASE 3 TOWER 10 (D) & T (Default on QPR)Noida2022-03
SUSHANT SERENE RESIDENCY PHASE 4 TOWER T8B & T12E& (Default on QPR)Noida2022-09
PARADISE CRYSTAL ZONE II (A, M, P & Q) (Default on QPR)Noida2023-06
SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-1 (B2B, D9 (Default on QPR)Noida2021-03
SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-2 (D1, B2A (Default on QPR)Noida2022-03
SUSHANT AQUAPOLIS, GROUP HOUSING, PHASE-3 (D2, D3, (Default on QPR)Noida2023-03
LIG ZONE I(L01 - LO6) (Default on QPR)Noida2022-01
LIG ZONE-II(L07 - L18) (Default on QPR)Noida2022-01
EWS AASRA ZONE II (E17-E32) (Default on QPR)Noida2022-06
EWS AASRA ZONE I (E01- E16) (Default on QPR)Noida2021-06
LIG ZONE-3 (TOWER L-19 TO L-36) (Default on QPR)Noida2023-06
EWS AASRA ZONE III (E33- E80) (Default on QPR)Noida2023-06
AASTHA MIG ZONE II (Default on QPR)Noida2022-12
AASTHA MIG ZONE III (M3, M7-M11) (Default on QPR)Noida2023-06
BUILTUPS ZONE I (Default on QPR)Noida2019-04
SUSHANT SERENE RESIDENCY PH1 T7B1 & T6DNoida2019-09
GOLD COAST CITY WALK (Default on QPR)Noida2026-07
SUSHANT SERENE RESIDENCY PH2 T3E,T4E,T5DNoida2021-09
AASTHA MIG ZONE I (M4 TO M6) (Default on QPR)Noida2022-06
GOLF GREEN AVENUE (Default on QPR)Noida2021-06
Registered, no progress filed yet (4)click to expand
ProjectCity
MIGSUN NEHRU PLACE 2Noida
MIGSUN CENTRAL MARKETNoida
MIGSUN NEHRU PLACE 3Noida
MIGSUN NEHRU PLACE 1Noida

RERA complaints & orders

Regulatory record

28 total complaints filed — above average for builders we track (51th percentile).

28
MahaRERA complaints

Most recent orders on the RERA register:

ProjectComplainantBenchDate
Tropez Business Center - Commercial phaseANIL BABASAHEB JADHAVHON. MEMBER IICopyright
Hubtown SolarisHubtown LimitedHON. CHAIRPERSON
Tropez Business Center - Commercial phaseSUYOG SIDRAM GHODAKEHON. MEMBER II
Tropez Business Center - Commercial phaseSANDEEP SHANTARAM MENGADEHON. MEMBER II
Tropez Business Center - Commercial phaseKULDEEP BHAGWANT JOSHIHON. MEMBER II

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Figures are Ansal's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.