01 Outlook & future development
The centre of the arc
is a future phase.
The blue land inside the orange Phase VIII boundary is Phase IX: 3.231 acres with a residential building-area allocation. Its final buildings, heights and delivery dates are not settled by this plan. The open centre cannot be priced as a permanent park.
Start with B’s north-west living side for inward landscape and greater separation from the northern service yard. Keep A’s north-west side as the next comparison, with more southern gate and road exposure at lower levels. Both need the future phase included in the view and price discussion.
Approved Site Plan ST-01 and Phasing Plan dated 6 March 2025 · Report pp. 2, 4–5 and 12. The recommendation concerns the living-room side, not the entrance direction.
Read what the phasing plan changes ↗