Developer RERA record

Central Park

Central Park has 18 RERA-registered projects: weak Gurugram delivery record (0/1 projects with OC); 12 projects under construction; 6 projects past their declared completion date. All figures are the developer's own regulator filings.

Mixed record
Delivery signal
12
Under construction
6
Past declared date
0/1
Gurugram with OC

Under construction

Under construction — 12 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
Central ParkMumbaipossession by Dec 2027
Central ParkMumbaipossession by Jul 2028
Central ParkMumbaipossession by Dec 2028
Central ParkMumbaipossession by Dec 2035
Central ParkMumbaipossession by Dec 2029
Central ParkMumbaipossession by Dec 2032
Central Park Wing-APunepossession by Dec 2029
THE Central Park Phase - IIPunepossession by Jun 2027
THE Central Park Phase - IIIPunepossession by Jun 2027
The Central Park Phase - IV Tower D4Punepossession by Dec 2031
THE Central Park Phase -IPunepossession by Dec 2026
The Central Park Phase- IV Tower D3Punepossession by May 2031
Considering a specific Central Park project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (6)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
CENTRAL PARK FLOWER VALLEY FLOORS AND VILLASGurugram2024-12
Central ParkMumbai2025-12
Central ParkMumbai2026-05
Central ParkMumbai2026-07
Central ParkPune2019-12
Central Park Residences C1Pune2026-05

Request the report on Central Park

We analyse Central Park in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Figures are Central Park's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.