Developer RERA record

Elan

Elan has 70 RERA-registered projects: mixed Gurugram delivery record (9/26 projects with OC); 2 projects under construction, Bengaluru averaging 8% construction; 8 projects past their declared completion date. All figures are the developer's own regulator filings.

2
Under construction
10
Completed / delivered
8
Past declared date
45%
Bengaluru inventory booked
29
RERA complaints filed

Public registration records

These records have not been classified as delivered, under construction or overdue. The declared date and status are filings, not a current site inspection.

SHLOK ELANZA

Ahmedabad · Registered: 2020-05-19 · Declared completion: 2025-06-30 · Filed status: New

Sai Empire

Chennai region · Registered: 2022-10-28

S.S.NAGAR

Chennai region · Registered: 2024-12-11 · Filed status: Completed

ACCESS SAI EMPIRE QUBE

Chennai region · Registered: 2024-10-01 · Declared completion: 2029-07-25 · Filed status: Progress of Work as on March 2026

SAI KAMALA NAGAR

Chennai region · Registered: 2026-09-22 · Filed status: Completed

Green Trails

Hyderabad region · Registered: 2022-09-29 · Declared completion: 2025-11-24

SN HEIGHTS

Hyderabad region · Declared completion: 2027-06-14

Under construction

Under construction — 2 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
ALINABengaluru10%
Melange One By VaishnodeviBengaluru5%
Considering a specific Elan project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (10)click to expand
ProjectCityStatus
SALARPURIA SATTVA ASHRAYABengaluruOC issued
COMMERCIAL COLONYGurugramOC issued
COMMERCIAL PROJECTGurugramOC issued
ELAN EPICGurugramOC issued
ELAN TOWN CENTRE, COMMERCIAL PROJECTGurugramOC issued
TRL RESIDENTIAL PLOTTED COLONYGurugramOC issued
URBAN CUBES 71GurugramOC issued
WHITELAND BLISSVILLEGurugramOC issued
WHITELAND BLISSVILLEGurugramOC issued
WHITELAND BLISSVILLEGurugramOC issued
Past declared date (8)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
KNS LAUREL PHASE-IIBengaluru2025-07
Smart neighbourhoodsBengaluru2019-03
SUBHA ELANBengaluru2023-03
KNS LAURELBengaluru2026-07
KNS ATHENABengaluru2024-08
KNS OJAS, SULIKEREBengaluru2019-11
ELAN EMPIREGurugram2026-04
ELAN PARADISEGurugram2025-09
Registered, no progress filed yet (16)click to expand
ProjectCity
ANANTHBengaluru
ASPEN ONEGurugram
ELAN EMPIREGurugram
ELAN IMPERIALGurugram
ELAN PARADISEGurugram
ELAN THE EMPERORGurugram
ELAN THE MARKGurugram
ELAN THE PRESIDENTIALGurugram
ELAN THE STATEMENTGurugram
THE ASPENGurugram
URBAN RESORTGurugram
URBAN RESORT PHASE-2Gurugram
URBAN RESORT PHASE-3Gurugram
URBAN RESORT PHASE 4Gurugram
URBAN RESORT PHASE 6Gurugram
WHITELAND ARENA 76Gurugram

RERA complaints & orders

Regulatory record

29 total complaints filed — above average for builders we track (76th percentile).

28
MahaRERA complaints
1
Karnataka RERA complaints

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Figures are Elan's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.