Developer RERA record

Emaar India

Emaar India has 21 RERA-registered projects: weak Gurugram delivery record (5/19 projects with OC); 2 projects under construction; 2 projects past declared completion date. All figures are the developer's own regulator filings.

Mixed record
Delivery signal
2
Under construction
5
Completed / delivered
2
Past declared date

Under construction

Under construction — 2 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
Casa VeneroMumbaipossession by Dec 2030
Emaar HeightMumbaipossession by Dec 2029
Considering a specific Emaar India project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (5)click to expand
ProjectCityStatus
EMAAR BUSINESS DISTRICT 114 NXTGurugramOC issued
EMAAR BUSINESS DISTRICT 75AGurugramOC issued
EMAAR BUSINESS DISTRICT (EBD) 114GurugramOC issued
EMAAR BUSINESS DISTRICT (EBD-89)GurugramOC issued
EMAAR BUSINESS DISTRICT (EBD-89 NXT)GurugramOC issued
Past declared date (2)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
EMAAR BUSINESS DISTRICT 99 (EBD 99)Gurugram2026-08
EMAAR BUSINESS DISTRICT 99 NXT (EBD 99 NXT)Gurugram2026-08
Registered, no progress filed yet (12)click to expand
ProjectCity
AMARISGurugram
EMAAR BUSINESS DISTRICT 65NXT (EBD 65NXT)Gurugram
EMAAR BUSINESS DISTRICT 83Gurugram
EMERALD HILLS - PHASE 2Gurugram
PLAZA 62Gurugram
SERENITY HILLS (PHASE-1)Gurugram
SERENITY HILLS (PHASE-2)Gurugram
THE 88Gurugram
URBAN ASCENTGurugram
URBAN OASIS - PHASE 1 & 2Gurugram
URBAN OASIS PHASE 4Gurugram
MARBELLA TERRACESGurugram

Figures are Emaar India's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.