Global Edifice

Global Edifice has 7 RERA-registered projects: 3 projects under construction, Bengaluru averaging 76% construction; 4 projects past their declared completion date. All figures are the developer's own regulator filings.

Flagged
Delivery signal
3
Under construction
4
Past declared date
26%
Bengaluru inventory booked

Under construction

Under construction — 3 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
LEGACYBengaluru99%
ORLEANBengaluru98%
THE CLANBengaluru30%
Considering a specific Global Edifice project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (4)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
GLOBAL EDIFICE INFRA CRESENTBengaluru2025-08
Green AppleBengaluru2019-09
GREEN APPLE HIKESBengaluru2022-07
CELESTABengaluru2025-12

Figures are Global Edifice's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.