Developer RERA record

Icon Infra

Icon Infra has 5 RERA-registered projects: 4 projects past their declared completion date. All figures are the developer's own regulator filings.

Flagged
Delivery signal
1
Completed / delivered
4
Past declared date
91%
Bengaluru inventory booked
Considering a specific Icon Infra project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (1)click to expand
ProjectCityStatus
GRAND ICON 3Bengaluru100% built
Past declared date (4)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
Icon SanctuaryBengaluru2018-12
ICONEST4Bengaluru2022-07
ICONEST 5Bengaluru2023-03
ICON MICASA (70.0% built)Bengaluru2024-12

Figures are Icon Infra's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.