Developer RERA record

Kanakia

Kanakia has 17 RERA-registered projects: 4 projects under construction; 13 projects past their declared completion date — a significant track-record flag. All figures are the developer's own regulator filings.

On the register
Delivery signal
4
Under construction
13
Past declared date

Under construction

Under construction — 4 projects

Construction % is the developer's own latest quarterly filing (Bengaluru, Gurgaon, Noida); MahaRERA files no construction %, so its projects show the declared possession date.

ProjectCityProgress / possession
Kanakia Beverly HeightsMumbaipossession by Dec 2027
Kanakia Future City DMumbaipossession by Jun 2027
Kanakia Silicon Valley FMumbaipossession by Dec 2026
Kanakia ValleyMumbaipossession by Dec 2030
Considering a specific Kanakia project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past declared date (13)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
Kanakia Future City AMumbai2025-06
Kanakia Future City BMumbai2025-06
Kanakia Future City CMumbai2025-06
Kanakia GreenbergMumbai2025-03
Kanakia HollywoodMumbai2019-09
Kanakia LevelsMumbai2021-10
Kanakia MiamiMumbai2020-09
Kanakia ParisMumbai2021-12
Kanakia RainforestMumbai2021-03
Kanakia SevensMumbai2021-12
Kanakia Wallstreet Wing AMumbai2019-12
Kanakia Zenworld Phase IMumbai2023-03
Kanakia Zenworld Phase IIMumbai2026-06

Request the report on Kanakia

We analyse Kanakia in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Figures are Kanakia's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.