Developer RERA record

Tulip Infratech

Tulip Infratech has 12 RERA-registered projects: weak Gurugram delivery record (2/7 projects with OC); 2 projects past declared completion date. All figures are the developer's own regulator filings.

2
Completed / delivered
2
Past declared date
28
RERA complaints filed

Public registration records

These records have not been classified as delivered, under construction or overdue. The declared date and status are filings, not a current site inspection.

Adarsh Tulip Skyview

Ahmedabad · Registered: 2021-04-22 · Declared completion: 2027-12-31 · Filed status: New

SILPA THE GROVE

Hyderabad region · Registered: 2023-04-18 · Declared completion: 2024-01-19

Considering a specific Tulip Infratech project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (2)click to expand
ProjectCityStatus
TULIP LEMONGurugramOC issued
TULIP YELLOWGurugramOC issued
Past declared date (2)click to expand

The declared completion date has passed with no completion certificate on record. Many projects receive RERA extensions, and MahaRERA publishes no OC at all — so this is the raw disclosure, not a verdict on delivery. Verify current status on the RERA portal.

ProjectCityDeclared date
TULIP PURPLE PHASE 2Gurugram2023-12
TULIP VIOLET PHASE-IIGurugram2020-12
Registered, no progress filed yet (4)click to expand
ProjectCity
ADITRI TULIPSBengaluru
TULIP CRIMSONGurugram
TULIP MONSELLA AND TULIP ATTILAGurugram
TULIP VIOLETGurugram

RERA complaints & orders

Regulatory record

28 total complaints filed — above average for builders we track (59th percentile).

28
MahaRERA complaints

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Figures are Tulip Infratech's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.