Gurgaon/Project record

HRERA · the public record

Palm Floors

SECTOR- 2 & 3, PATAUDI · Vk & Sons Infratech

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
68units in latest filingQ2 2026 filing
0units sold that quarterQ2 2026 filing
14 Jun 2029registration expiryHRERA registration · read 22 Oct 2026

Free project details

Registration read 22 Oct 2026

RERA details for Palm Floors

HRERA ·

Escrow account

What has moved through the RERA escrow account?

Across 3 filed quarterly reports, Palm Floors records ₹6.27 Cr paid into and ₹5.99 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹28 L.

₹6.27 Cr

into the escrow account

₹5.99 Cr

withdrawn

₹28 L

latest balance

Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.

Source · HRERA quarterly progress reports

Official Unit Inventory

68 apartments filed across 1 carpet-area configurations, 17 towers, carpet areas from 714 to 714 sq ft. These are the carpet areas the developer filed with HRERA — match the unit a broker quotes you against this table; a "1,650 sq ft" pitch should map to a filed configuration here (carpet area is the RERA-defined saleable floor).

Carpet area(metric)Units of this size
714 sq ft66.3 sq m68

Sales Traction, Quarter by Quarter

Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.

QuarterUnits bookedTotal units
2025 Q42768
2026 Q1368
2026 Q2068

Escrow Account Activity

Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.

QuarterDepositedWithdrawnBalance
2025 Q4₹2.61 Cr₹2.50 Cr₹11 L
2026 Q1₹2.58 Cr₹2.69 Cr₹0 L
2026 Q2₹1.08 Cr₹80 L₹28 L

Location & Connectivity

The nearest of the listed job hubs is about 3 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Golf Course Road belt3 km
Cyber City / DLF Cyber Hub7 km
Udyog Vihar7 km
IGI Airport, Delhi14 km
IMT Manesar16 km
Connaught Place, Delhi26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Vk & Sons Infratech.

Other RERA-registered projects in Gwal Pahari

Major developers building in Gwal Pahari

Figures are the developer's own quarterly disclosures on the Haryana RERA register. "Sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Gurgaon project-health tool.

Registration last seen on RERA: 22 Oct 2026. Document and inventory dates are shown in their sections.