Mumbai/Project record

MahaRERA · the public record

aatmarampark

Palghar · Sanjeev Gyaninder Mittal

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000016597

Delivery and registration

When is the project declared for completion?

aatmarampark is registered with MahaRERA as P99000016597 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

51months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000016597
Registered on23 May 2018
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for aatmarampark record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for aatmarampark in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Aatmaram Park Wing A1G+430 Jun 2021
Aatmaram Park Wing B1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2021DUE TO COVID -19 AND LACK OF LABOUR AND MATERIAL SUPPLY AND DUE TO FINANCIAL CRISIS
30 Jun 202131 Dec 2021SIR, WE WANT AN EXTENSION FOR A PROJECT AGAIN AS DUE TO COVID 19 PANDEMIC OUR PROJECT IS NOT BEEN COMPLETED DUE TO SHORTAGE OF LABOUR AS WELL AS MATERIAL. SIR PLEASE GRANT US ANOTH

Location, Land & Connectivity

Located at Palghar, Palghar, 401501. Per the filed land record, the plot is bounded to the north by 1, to the south by 1, to the east by 1 and to the west by 1. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Boisar

Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises
Marathe Complex
possession by Dec 2026 · Gprs Realty
Rajhans United Regency III
possession by Dec 2026 · Rajhans Homes
Yash Padma
possession by Dec 2026 · SAI Shraddha Enterprises

Other RERA-registered projects in Palghar

Aayush Nine
declared completion Dec 2024 · Pavankumar Rajdev Pandey
Abdul Hakeem Heights A Wing
possession by Mar 2029 · Not Available
Abhi Garden 3
possession by Dec 2028 · Sambhav Enterprises
Abhi Paradise
declared completion Dec 2023 · Ramvilash Singh
Abhishek Apartment
declared completion Dec 2025 · Sandeep Ghanshyam Vyas
Abhishek Appartment
possession by Dec 2026 · OM Shri SAI Construction

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026