Bhavya Heights

Mumbai Suburban · Bhavya Infrastructures India Private Limited

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗
30 Sep 2022declared completionMahaRERA registration · read 18 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 18 Jul 2026

Free project details

Registration read 18 Jul 2026

RERA details for Bhavya Heights

MahaRERA · P51800003431

Delivery and registration

When is the project declared for completion?

Bhavya Heights is registered with MahaRERA as P51800003431 and the promoter has declared completion for 30 Sep 2022.

30 Sep 2022

declared completion

49months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP51800003431
Registered on05 Aug 2017
Promoter-declared completion30 Sep 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Bhavya Heights record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Bhavya Heights in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
Bhavya Heights1G+1930 Jun 2021

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Bhavya Heights, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000029273402/10/2022Abbas Alimohammad Kachwala vs M/s. BHAVYA INFRASTRUCTURES (INDIA) PRIVATE LIMITEDorder passed
CC00600000029273502/10/2022Abbas Alimohammad Kachwala vs M/s. BHAVYA INFRASTRUCTURES (INDIA) PRIVATE LIMITEDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020As per new MCGM norms, the promoter is entitled for procuring incentive FSI based on road width, which the promoter has already obtained. Hence, the promoter required extension of
30 Dec 202031 Mar 2022Due to the ongoing pandemic Covid - 19, there has been a shortage of workers, which has led to the delay in the completion of finishing works of our project. The Civil Work upto 18

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by M G Road, to the south by Badri Building, to the east by Bora Masjid and to the west by Anand Nagar. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 9 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park12 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kandivali West

Goyal Aspire
declared completion Oct 2026 · Nexa Buildcon LLP
Kandivali Hanuman Co-Op Housing Society Ltd
declared completion Nov 2026 · Kandivali Hanuman Co-Op Housing Society
Avenue Wing B
declared completion Dec 2026 · Dharmesh Constructions Private Limited
RAM Chhaya
Not filing quarterly progress reports · declared completion Dec 2026 · Prime Infra
Rock Highland
declared completion Dec 2026 · Rock Estates
Sale Bldg NO. 6 Wing Known AS Northern Supremus & Northern Hills Building NO. 1 & 2
declared completion Dec 2026 · N.rose Developers PVT LTD
More projects in Mumbai Suburban

Other RERA-registered projects in Mumbai Suburban

Bhawani Heights
declared completion Jun 2025 · M/s Bhawani Developers
Bhoomi Airavat
declared completion Dec 2031 · Bhoomi Shashwat Estate Private Limited
Bhoomi Amogh
declared completion Dec 2029 · Bhoomi Realty AND Developers LLP
Bhoomi Green Hill
declared completion Dec 2031 · Bhumi Infrastructure Realty AND Housing
Bhoomi Prarambh
declared completion Dec 2025 · Bhoomi Shashwat Estate Pvt. Ltd.
Bhoomi Pratishtha
declared completion Oct 2026 · Bhoomi Shashwat Estate Pvt. Ltd.

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.