Mumbai/Project record

MahaRERA · the public record

BHAVYA HEIGHTS

GLOBAL CITY, HDIL · MORYA REALTORS

Project Review · example purchase

Spending a few crores on a unit? ₹4,999 to check what you’re buying.

Check what the plans put beside your unit, below it and in front of it. The view, nearby buildings and shared facilities can change what you are buying.

47units filed as unsoldInventory · 22 October 2026
30 Jun 2027declared completionMahaRERA registration · read 18 Jul 2026
97registered unitsMahaRERA registration · read 18 Jul 2026

See the report before you buy

Avoid bad decisions, only go for the best units.

Read the complete sample: unit choices, layout illustrations, important risks and questions for the builder. Its findings concern the named sample, not this project.

Read the Project Review sample ↗

Free project details

Registration read 18 Jul 2026

RERA details for BHAVYA HEIGHTS

MahaRERA · P99000011803

Delivery and registration

When is the project declared for completion?

BHAVYA HEIGHTS is registered with MahaRERA as P99000011803 and the promoter has declared completion for 30 Jun 2027.

30 Jun 2027

declared completion

8months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 18 Jul 2026

MahaRERA registrationP99000011803
Registered on31 Aug 2017
Promoter-declared completion30 Jun 2027
Current statusCertificate Signed
Against today8 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BHAVYA HEIGHTS record the entries listed below.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 18 Jul 2026

View the free 14-item checklist →

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (2025-06-30).

Construction

How much construction cost has been reported?

In BHAVYA HEIGHTS, ₹10.42 Cr of a declared ₹13.86 Cr estimated project cost is reported as incurred, about 75.2%, as at the last certified filing with MahaRERA.

75.2%

₹10.42 Cr

of ₹13.86 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 18 Jul 2026

Sales

How many are filed as sold or booked?

In BHAVYA HEIGHTS, 50 of 97 units filed with MahaRERA are recorded as sold or booked, about 52%, and 47 are filed as unsold.

52%sold or booked

50 of 97 units

₹11.01 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹9.60 Cr (about 87%) is recorded as collected and ₹1.41 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 18 Jul 2026

Filed agreement values: across 50 sold or booked entries with usable filed values and areas, the effective carpet rate is ₹5,344/sqft, with eight in ten falling between ₹4,551 and ₹6,793 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, unit by unit

Read from MahaRERA on 22 October 2026

MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for sold or booked entries the filed agreement value — the consideration filed for that specific unit. On this project 50 units carry one, and 47 of the 97 are recorded unsold.

Here is one unit filed as unsold, beside the amounts filed for comparable units:

UnitCarpetFiled comparisonBased on
101432 sqftRs 23.00 lakh typical, over Rs 17.80 lakh to Rs 32.76 lakh12 filed · similar area (within 2%), elsewhere in project

A filed consideration is the amount the promoter reported for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In BHAVYA HEIGHTS, 46 of the 47 unsold units have filed sales to compare with. The Sales Report gives each of them its own row — the filed agreements behind its comparison listed in full, the government reckoner value the promoter filed against it, and mortgage status where the filing supplies it. Missing mortgage information is not confirmation that a unit is free of a mortgage. Built from the filing itself, sent by email.

See the other 46 units — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16 and 97 units are registered across the project.

BuildingWingsFloorsUnitsDeclared completion
BHAVYA HEIGHTS1G+169730 Jun 2020

Unit mix on the filing: 88 residential and 9 non-residential.

Legal and disputes

What disputes are disclosed?

19 complaints are on the MahaRERA record for BHAVYA HEIGHTS, with orders passed in 19 of them.

19complaints

19with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 18 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000008977918/06/2019PRADEEP PATIL vs MORYA REALTORSorder passed
CC00600000020993808/02/2022MAHENDRA MISHRA & ASHA M MISHRA vs 1. MORYA REALTORS BUILDERS AND DEVELOPERS 2. M/S MORYA BUILDERS 3.M/S HOUSING DEVELOPMENT AND INFRASorder passed
CC00600000019831111/09/2021Haricharan Yadav vs Morya Realtorsorder passed
CC00600000019804406/09/2021AYESSPEA HOLDINGS AND INVESTMENTS PVT LTD vs Morya Realtorsorder passed
CC00600000019806106/09/2021AYESSPEA HOLDINGS AND INVESTMENT PVT LTD vs Morya Realtorsorder passed
CC00600000019806206/09/2021AYESSPEA HOLDINGS AND INVESTMENT PVT LTD vs Morya Realtorsorder passed
CC00600000019807506/09/2021AYESSPEA HOLDINGS AND INVESTMENTS PVT LTD vs Morya Realtorsorder passed
CC00600000019809706/09/2021Ayesspea Holdings and Investments Private Limited vs Morya Realtorsorder passed
CC00600000019809907/09/2021Ayesspea Holdings and Investments Private Limited vs Morya Realtorsorder passed
CC00600000019810107/09/2021Ayesspea Holdings and Investments Private Limited vs Morya Realtorsorder passed
CC00600000019810207/09/2021Ayesspea Holdings and Investments Private Limited vs Morya Realtorsorder passed
CC00600000019811107/09/2021Ayesspea Holdings and Investments Private Limited vs Morya Realtorsorder passed
CC00600000019816907/09/2021Ayesspea Holdings and Investments Private Limited vs Morya Realtorsorder passed
CC00600000019817013/09/2021Ayesspea Holdings and Investments Private Limited vs Morya Realtorsorder passed
CC00600000019817213/09/2021Ayesspea Holdings and Investments Private Limited vs Morya Realtorsorder passed
CC00600000020975225/01/2022Vaishali Mahajan vs Morya Realtorsorder passed
CC00600000020993408/02/2022Ramesh Chiluka vs Morya Realtorsorder passed
CC1240044918/10/2024Jyoti R Patil vs MORYA REALTORSorder passed
CC1250069327/02/2025SUBODH SUSHILCHANDRA PEDNEKAR vs MORYA REALTORSorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2020Due to differences among the Partners.
30 Jun 202030 Sep 2022DUE TO COVID PANDEMIC AND FINANCIAL CRISES
30 Sep 202230 Apr 2024PROJECT EXTENT DUE TO FINANCIAL CRISES AND SHORTAGE OF MATERIALS.
30 Apr 202430 Jun 2027Due to differences among the Partners. now short out and works at completion stage.

Location, Land & Connectivity

Located at GLOBAL CITY, HDIL, CHIKHAL DONGERE ROAD, Vasai, Palghar, 401303. Per the filed land record, the plot is bounded to the north by WIDE D P ROAD, to the south by GARDEN, to the east by WING E-2 and to the west by WING D-2. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest of the listed job hubs is about 34 km in a straight line from the mapped location. Road distance and travel time will differ.

LandmarkStraight-line
Andheri MIDC / SEEPZ34 km
Powai / Hiranandani business park35 km
Chhatrapati Shivaji Int'l Airport39 km
Bandra Kurla Complex (BKC)41 km
Lower Parel / Worli business district49 km
Nariman Point / Fort58 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Virar West

Dattachhaya
declared completion Nov 2026 · Jagdish Manohar Mhatre
Solaris Wing E-1 Hdil Layout
declared completion Dec 2026 · Sunshine Developers
Star ERA
declared completion Dec 2026 · Star Builders & Developers
Sugandhi Square
declared completion Dec 2026 · R. N. Realty
Vitthal Haven
declared completion Dec 2026 · Sushila Builders & Developers
Anand Kirti Tower
declared completion Dec 2026 · S R And Shah Developers
More projects in Palghar

Other RERA-registered projects in Palghar

Bhoomi Builders AND Developers
declared completion Jun 2025 · Bhoomi Builders AND Developers
Bhoomi Classic Building No. 02
declared completion Dec 2028 · Apna Sai Builders And Developers
Bhumika Developer
declared completion Jun 2024 · Bhumika Developers
Birla Mrida
declared completion Mar 2029 · Birla Estates Private Limited
Bitcon Paradise Complex
declared completion Dec 2030 · Kiran Development Corporation
Bitcon Paradise Complex -Ecstasy
declared completion Aug 2025 · Kiran Development Corporation

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Registration details and regulatory notices are drawn from the held MahaRERA record. See more Mumbai, Thane & the MMR projects.

Registration last seen on RERA: 25 Oct 2026. Document and inventory dates are shown in their sections.